8642 N COMANCHE AVE ADU 91306

Certificate Information: 8642 N COMANCHE AVE ADU 91306

Application / Permit
25010-20000-00439
Plan Check / Job No.
B25VN01331
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 23'-1" x 34'-8" ONE-STORY ACCESSORY DWELLING UNIT PER GC 66323(a)(2); NFPA-13D THRU-OUT
Permit Issued
Issued on 5/28/2025
Issuing Office
Current Status
Issued on 5/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/21/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 SEAN SHAHMIRI
Corrections Issued 2/4/2025 SEAN SHAHMIRI
Quality Review Completed 2/4/2025 STEVEN KIM
Applicant returned to address corrections 5/21/2025 SEAN SHAHMIRI
Plan Check Approved 5/22/2025 SEAN SHAHMIRI
Plan Check Approved 5/28/2025 INTERNET PERMIT
Issued 5/28/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/5/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/5/2025 CARLOS AGUILERA
Sewer availability Cleared 3/12/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/1/2025 CARLOS AGUILERA
Hydrant and Access approval Cleared 5/21/2025 PATRICK PEREZ

Contact Information

Contractor Potato Construction Inc; Lic. No.: 1003152-B       ,
Engineer Gao,, Jianfeng; Lic. No.: C88478 18825 ELMHURST ST      ROWLAND HEIGHTS, CA 91748

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/15/2025 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 7/24/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 9/11/2025 Corrections Issued JEFFREY HARTLINE
ELECTRICAL-Rough 9/11/2025 Corrections Issued JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Partial Approval JEFFREY HARTLINE
Green Building Rough 9/11/2025 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 9/11/2025 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Rough 9/11/2025 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 9/11/2025 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Partial Approval JEFFREY HARTLINE
HVAC-Rough 10/16/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 10/16/2025 Corrections Issued JEFFREY HARTLINE
Sewer 10/16/2025 Approved JEFFREY HARTLINE
Shower Pan 12/9/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 1/8/2026 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Rough 1/8/2026 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 1/27/2026 Corrections Issued JEFFREY HARTLINE
ELECTRICAL-Rough 1/27/2026 Approved JEFFREY HARTLINE
Green Building Rough 1/27/2026 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 1/27/2026 Approved JEFFREY HARTLINE
PLUMBING-Rough 1/27/2026 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 1/27/2026 Approved JEFFREY HARTLINE
Insulation 2/4/2026 Approved JEFFREY HARTLINE
Drywall Nailing 2/11/2026 Approved JEFFREY HARTLINE
ELECTRICAL-Final 6/23/2026 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Final 6/23/2026 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Final 6/23/2026 Not Ready for Inspection JEFFREY HARTLINE