8907-8909 N AMIGO AVE 91324

Certificate Information: 8907-8909 N AMIGO AVE 91324

Application / Permit
25010-20000-00389
Plan Check / Job No.
B25VN02185
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GC 66323(a)(1) AND 66333
Permit Issued
Issued on 4/30/2025
Issuing Office
Current Status
Issued on 4/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/29/2025 APPLICANT
Assigned to Plan Check Engineer 2/3/2025 ISIS ARGUETA
Corrections Issued 2/4/2025 ISIS ARGUETA
Applicant returned to address corrections 2/12/2025 NAREG ATARIAN
Applicant returned to address corrections 3/14/2025 ALEC MOUSAKHANIAN
Plan Check Approved 3/18/2025 LUISANGEL VALENZUELA
Issued 4/30/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 2/19/2025 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 2/20/2025 EDGAR ALCARAZ
Address approval Cleared 3/4/2025 EDGAR ALCARAZ

Contact Information

Contractor Sire Energy Inc; Lic. No.: 1027415-B       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/2/2025 No Access for Inspection KRISTEN CAUSEY
Footing/Foundation/Slab 5/6/2025 Approved KRISTEN CAUSEY
PLUMBING-Rough 5/6/2025 Partial Approval KRISTEN CAUSEY
ELECTRICAL-Rough 5/16/2025 Approved KRISTEN CAUSEY
HVAC-Rough 5/16/2025 Approved KRISTEN CAUSEY
PLUMBING-Rough 5/16/2025 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 5/29/2025 Approved KRISTEN CAUSEY
Green Building Rough 5/29/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 5/29/2025 Partial Approval KRISTEN CAUSEY
Insulation 6/2/2025 Approved TROY SANDERS
Interior/Exterior Lathing 6/2/2025 Approved TROY SANDERS
Shower Pan 6/2/2025 Approved TROY SANDERS
Drywall Nailing 6/9/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Final 10/9/2025 Approved KRISTEN CAUSEY
Final 10/9/2025 Corrections Issued KRISTEN CAUSEY
Green Building Final 10/9/2025 Not Ready for Inspection KRISTEN CAUSEY
HVAC-Final 10/9/2025 Approved KRISTEN CAUSEY
PLUMBING-Final 10/9/2025 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Approved KRISTEN CAUSEY
Smoke Detectors 10/9/2025 Approved KRISTEN CAUSEY
Final 10/10/2025 Corrections Issued KRISTEN CAUSEY