144 1/4-1/2 W 83RD ST 90003
Certificate Information: 144 1/4-1/2 W 83RD ST 90003
- Application / Permit
- 25010-20000-00381
- Plan Check / Job No.
- B25VN02124
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New one story detached building containing two new ADU's per GC 66323(a)(4).
- Permit Issued
- Issued on 6/18/2025
- Issuing Office
- Current Status
- CofO Issued on 5/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | MARCELA FRANQUEZ |
| Corrections Issued | 2/25/2025 | MARCELA FRANQUEZ |
| Quality Review Completed | 2/28/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 4/16/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 6/12/2025 | MARCELA FRANQUEZ |
| Issued | 6/18/2025 | APPLICANT |
| CofO in Progress | 5/14/2026 | RAUL BARAJAS |
| Permit Finaled | 5/16/2026 | DEROLD HAUFF |
| CofO Issued | 5/16/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/27/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 3/12/2025 | WALLIE JONG |
| Sewer availability | Cleared | 3/12/2025 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 4/14/2025 | KENNETH FRASER |
| Miscellaneous | Cleared | 4/17/2025 | JASON CHAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/2/2025 | Approved | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 9/4/2025 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 9/4/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 9/25/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 10/2/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 10/6/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 10/6/2025 | Corrections Issued | LUIS CASTRO |
| Interior/Exterior Lathing | 10/6/2025 | Partial Approval | LUIS CASTRO |
| Verify Sprinkler Sign Off | 10/6/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 10/7/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 10/8/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 10/8/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 10/14/2025 | Approved | DEVON JACKSON |
| Drywall Nailing | 10/20/2025 | Approved | ANTHONY RAMOS |
| Sewer | 11/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 11/4/2025 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 11/4/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 11/18/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Shower Pan | 11/18/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 11/21/2025 | Not Ready for Inspection | ANTHONY RAMOS |
| Shower Pan | 11/21/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 11/26/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 12/4/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 1/23/2026 | Approved | JOHN QUINTANILLA |
| HVAC-Final | 1/23/2026 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Final | 1/27/2026 | Approved | JOHN QUINTANILLA |
| Final | 1/27/2026 | OK to Issue CofO | JOHN QUINTANILLA |
| Green Building Final | 1/27/2026 | Approved | JOHN QUINTANILLA |
| HVAC-Final | 1/27/2026 | Approved | JOHN QUINTANILLA |
| PLUMBING-Final | 1/27/2026 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Not Required | JOHN QUINTANILLA |
| Service/Power Release | 1/27/2026 | Approved | JOHN QUINTANILLA |
| Smoke Detectors | 1/27/2026 | Approved | JOHN QUINTANILLA |