11748 W BLIX ST 91607

Certificate Information: 11748 W BLIX ST 91607

Application / Permit
25010-20000-00369
Plan Check / Job No.
B25VN02065
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 54'9" X 45' TWO STORY SFD WITH ATTACHED TWO CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/5/2025
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 RARES BODEA
Corrections Issued 2/3/2025 RARES BODEA
Quality Review Completed 2/3/2025 STEVEN KIM
Building Plans Picked Up 2/5/2025 APPLICANT
Plan Check Approved 3/5/2025 RARES BODEA
Issued 3/5/2025 APPLICANT
CofO in Progress 1/21/2026 JAVIER RAMOS JR
CofO in Progress 3/28/2026 RAUL OLAGI
Permit Finaled 4/2/2026 RUBEN SALAS
CofO Issued 4/2/2026 RUBEN SALAS
Permit Finaled 4/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/3/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/4/2025 CARLOS AGUILERA
Sewer availability Cleared 2/4/2025 CARLOS AGUILERA
Miscellaneous Cleared 2/5/2025 JOANNA MARROQUIN
Specific Plan Cleared 2/5/2025 JOANNA MARROQUIN
ZI Cleared 2/5/2025 JOANNA MARROQUIN
ZI Cleared 2/5/2025 JOANNA MARROQUIN
Low Impact Development (LID) Cleared 2/11/2025 SARAH YOUSSEF
Hydrant and Access approval Cleared 2/14/2025 LAVEON RIDER
Trees in Parkway Cleared 2/19/2025 BRANDON WONG
Permit Cleared 2/20/2025 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/8/2025 Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 4/15/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 4/15/2025 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 4/30/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/5/2025 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/5/2025 Corrections Issued JAVIER RAMOS JR
Green Building Rough 6/5/2025 Approved JAVIER RAMOS JR
HVAC-Rough 6/5/2025 Approved JAVIER RAMOS JR
Special/Order Compliance 6/5/2025 No Access for Inspection JAVIER RAMOS JR
Underground Mechanical 6/5/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 6/10/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/10/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/13/2025 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Approved JAVIER RAMOS JR
Shower Pan 6/13/2025 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 6/13/2025 Approved JAVIER RAMOS JR
Insulation 6/25/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/25/2025 Approved JAVIER RAMOS JR
Drywall Nailing 7/1/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 12/9/2025 Corrections Issued CRAIG DAVIS
HVAC-Final 12/9/2025 Corrections Issued CRAIG DAVIS
PLUMBING-Final 12/9/2025 Corrections Issued CRAIG DAVIS
Service/Power Release 12/9/2025 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 12/19/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/19/2025 Approved JAVIER RAMOS JR
Final 12/19/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 12/19/2025 Approved JAVIER RAMOS JR
HVAC-Final 12/19/2025 Approved JAVIER RAMOS JR
MERV13>=Final 12/19/2025 Approved JAVIER RAMOS JR
MERV13>=Rough 12/19/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 12/19/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 12/19/2025 Approved JAVIER RAMOS JR
Smoke Detectors 12/19/2025 Approved JAVIER RAMOS JR
Final 1/21/2026 OK to Issue CofO JAVIER RAMOS JR