7847 N RHODES AVE 91605

Certificate Information: 7847 N RHODES AVE 91605

Application / Permit
25010-20000-00366
Plan Check / Job No.
B25VN02008
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW DETACHED 45'X28' ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(b)(1). <ALL ELECTRIC BLDG>
Permit Issued
Issued on 2/13/2025
Issuing Office
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2025 APPLICANT
Assigned to Plan Check Engineer 2/3/2025 HAYATO TSUCHIYA
Corrections Issued 2/3/2025 HAYATO TSUCHIYA
Building Plans Picked Up 2/6/2025 APPLICANT
Plan Check Approved 2/13/2025 ISIS ARGUETA
Issued 2/13/2025 APPLICANT
CofO in Progress 5/5/2025 NICHOLAS TROWBRIDGE
Permit Finaled 5/15/2025 RUBEN SALAS
CofO Issued 5/15/2025 RUBEN SALAS
Permit Finaled 5/15/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/4/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/4/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/4/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/5/2025 LEE GUILBEAUX
Sewer availability Cleared 2/5/2025 LEE GUILBEAUX
Construction near power lines Cleared 2/12/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/26/2025 Approved MATTHEW NELSON
Underground Mechanical 2/26/2025 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 2/27/2025 Approved JACK KARGODORIAN
Underground Mechanical 2/27/2025 Approved JACK KARGODORIAN
Footing/Foundation/Slab 2/28/2025 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 3/12/2025 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 3/12/2025 Approved MATTHEW NELSON
Green Building Rough 3/12/2025 Approved MATTHEW NELSON
HVAC-Rough 3/12/2025 Approved MATTHEW NELSON
PLUMBING-Rough 3/12/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/14/2025 Partial Approval MATTHEW NELSON
Insulation 3/17/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/17/2025 Not Ready for Inspection MATTHEW NELSON
Shower Pan 3/17/2025 Approved MATTHEW NELSON
Drywall Nailing 3/21/2025 Approved MATTHEW NELSON
Underground Mechanical 3/21/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/30/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 4/30/2025 Approved NICHOLAS TROWBRIDGE
Final 4/30/2025 OK to Issue CofO NICHOLAS TROWBRIDGE
Green Building Final 4/30/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Final 4/30/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Final 4/30/2025 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 4/30/2025 SGSOV Approved NICHOLAS TROWBRIDGE
Service/Power Release 4/30/2025 Approved NICHOLAS TROWBRIDGE
Smoke Detectors 4/30/2025 Approved NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 4/30/2025 Approved NICHOLAS TROWBRIDGE