1023 N GALLOWAY ST 90272

Certificate Information: 1023 N GALLOWAY ST 90272

Application / Permit
25010-20000-00363
Plan Check / Job No.
B25VN01995
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 6/11/2025
Issuing Office
Valley
Current Status
Issued on 6/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/27/2025 APPLICANT
Assigned to Plan Check Engineer 1/27/2025 OMAR GARNICA
Corrections Issued 1/27/2025 OMAR GARNICA
Building Plans Picked Up 1/31/2025 APPLICANT
Plan Check Approved 2/27/2025 OMAR GARNICA
No Progress 3/25/2025 OMAR GARNICA
Plan Check Approved 5/14/2025 OMAR GARNICA
Issued 6/11/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/4/2025 HISASHI KOBAYAKAWA
Sewer availability Cleared 2/4/2025 HISASHI KOBAYAKAWA
Sewer availability Cleared 2/4/2025 HISASHI KOBAYAKAWA
Public Works-Sewers Cleared 2/4/2025 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 2/5/2025 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 2/11/2025 RUEL COLE

Contact Information

Contractor Socal Construction Management Inc; Lic. No.: 984621-B 24767 VIA DEL LLANO      CALABASAS, CA 91302
Engineer Basma,, Ali J; Lic. No.: C53080 6047 TAMPA AVE   SUITE 304    TARZANA, CA 91356

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/1/2025 Conditional Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 10/24/2025 Approved TEMISTOCLES CAAL
Footing/Foundation/Slab 10/24/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Partial Approval TEMISTOCLES CAAL
Deputy Pre-Stress Concrete 2/4/2026 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 2/12/2026 Approved MICHAEL ALLEN
Underground Mechanical 3/25/2026 Approved TEMISTOCLES CAAL
HVAC-Rough 3/26/2026 Partial Approval TEMISTOCLES CAAL
HVAC-Rough 4/2/2026 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 4/17/2026 Approved TEMISTOCLES CAAL
PLUMBING-Rough 4/17/2026 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 4/22/2026 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 4/28/2026 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 4/29/2026 Approved TEMISTOCLES CAAL
Green Building Rough 4/29/2026 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 4/29/2026 Partial Approval TEMISTOCLES CAAL
Verify Sprinkler Sign Off 4/29/2026 Approved TEMISTOCLES CAAL