1023 N GALLOWAY ST 90272
Certificate Information: 1023 N GALLOWAY ST 90272
- Application / Permit
- 25010-20000-00363
- Plan Check / Job No.
- B25VN01995
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 6/11/2025
- Issuing Office
- Valley
- Current Status
- Issued on 6/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2025 | OMAR GARNICA |
| Corrections Issued | 1/27/2025 | OMAR GARNICA |
| Building Plans Picked Up | 1/31/2025 | APPLICANT |
| Plan Check Approved | 2/27/2025 | OMAR GARNICA |
| No Progress | 3/25/2025 | OMAR GARNICA |
| Plan Check Approved | 5/14/2025 | OMAR GARNICA |
| Issued | 6/11/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/4/2025 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 2/4/2025 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 2/4/2025 | HISASHI KOBAYAKAWA |
| Public Works-Sewers | Cleared | 2/4/2025 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2025 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 2/11/2025 | RUEL COLE |
Contact Information
| Contractor | Socal Construction Management Inc; Lic. No.: 984621-B | 24767 VIA DEL LLANO CALABASAS, CA 91302 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 6047 TAMPA AVE SUITE 304 TARZANA, CA 91356 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/1/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 10/24/2025 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 10/24/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Pre-Stress Concrete | 2/4/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Approved | MICHAEL ALLEN |
| Underground Mechanical | 3/25/2026 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 3/26/2026 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 4/2/2026 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 4/17/2026 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/17/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/22/2026 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 4/28/2026 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 4/29/2026 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 4/29/2026 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 4/29/2026 | Partial Approval | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 4/29/2026 | Approved | TEMISTOCLES CAAL |