7032 N YARMOUTH AVE 91335

Certificate Information: 7032 N YARMOUTH AVE 91335

Application / Permit
25010-20000-00354
Plan Check / Job No.
B25VN01933
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE AND KEEP (E) FOOTING TO CREATE A NEW 2-STORY 22'-0" x 30'-6" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d) PER ENGINEERING
Permit Issued
Issued on 9/3/2025
Issuing Office
Valley
Current Status
CofO in Progress on 6/12/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/27/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 ALFRED RAMIREZ
Corrections Issued 2/11/2025 ALFRED RAMIREZ
Quality Review Completed 2/13/2025 STEVEN KIM
Building Plans Picked Up 2/14/2025 APPLICANT
Plan Check Approved 5/2/2025 ALFRED RAMIREZ
Issued 9/3/2025 APPLICANT
CofO in Progress 6/12/2026 ARUTYUN MADATYAN

Permit Application Clearance Information

Address approval Cleared 2/20/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/20/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 2/20/2025 RYAN CASTRO
Sewer availability Cleared 2/20/2025 RYAN CASTRO

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/25/2025 Approved ARUTYUN MADATYAN
Deputy Drilled-In Anchors 9/29/2025 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 10/2/2025 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 10/2/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 10/2/2025 Partial Approval ARUTYUN MADATYAN
Sewer 10/2/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 10/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Rough 10/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
Deputy Wood Construction 10/30/2025 Conditional Approval ROBERT GOLD
Interior/Exterior Lathing 11/12/2025 Partial Approval ARUTYUN MADATYAN
ELECTRICAL-Rough 12/8/2025 Approved JUAN ALVARADO
HVAC-Rough 12/8/2025 Approved JUAN ALVARADO
PLUMBING-Rough 12/8/2025 Corrections Issued JUAN ALVARADO
BUILDING-Rough-Frame 12/17/2025 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Rough 12/17/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 12/17/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 1/8/2026 Approved ARUTYUN MADATYAN
Insulation 1/8/2026 Approved ARUTYUN MADATYAN
Shower Pan 1/8/2026 Approved ARUTYUN MADATYAN
Drywall Nailing 1/30/2026 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 1/30/2026 Partial Approval ARUTYUN MADATYAN
ELECTRICAL-Final 5/8/2026 Not Ready for Inspection ARUTYUN MADATYAN
Final 5/8/2026 Corrections Issued ARUTYUN MADATYAN
Green Building Final 5/8/2026 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 5/8/2026 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Final 5/8/2026 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 5/8/2026 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 5/8/2026 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 6/4/2026 Approved ARUTYUN MADATYAN
Final 6/4/2026 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 6/4/2026 Approved ARUTYUN MADATYAN
HVAC-Final 6/4/2026 Approved ARUTYUN MADATYAN
Final 6/11/2026 OK to Issue CofO ARUTYUN MADATYAN