7032 N YARMOUTH AVE 91335
Certificate Information: 7032 N YARMOUTH AVE 91335
- Application / Permit
- 25010-20000-00354
- Plan Check / Job No.
- B25VN01933
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND KEEP (E) FOOTING TO CREATE A NEW 2-STORY 22'-0" x 30'-6" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d) PER ENGINEERING
- Permit Issued
- Issued on 9/3/2025
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 6/12/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2025 | ALFRED RAMIREZ |
| Corrections Issued | 2/11/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 2/13/2025 | STEVEN KIM |
| Building Plans Picked Up | 2/14/2025 | APPLICANT |
| Plan Check Approved | 5/2/2025 | ALFRED RAMIREZ |
| Issued | 9/3/2025 | APPLICANT |
| CofO in Progress | 6/12/2026 | ARUTYUN MADATYAN |
Permit Application Clearance Information
| Address approval | Cleared | 2/20/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 2/20/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 2/20/2025 | RYAN CASTRO |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/25/2025 | Approved | ARUTYUN MADATYAN |
| Deputy Drilled-In Anchors | 9/29/2025 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 10/2/2025 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 10/2/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 10/2/2025 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 10/2/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 10/29/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Rough | 10/29/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Deputy Wood Construction | 10/30/2025 | Conditional Approval | ROBERT GOLD |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 12/8/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 12/8/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 12/8/2025 | Corrections Issued | JUAN ALVARADO |
| BUILDING-Rough-Frame | 12/17/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 12/17/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/17/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 1/8/2026 | Approved | ARUTYUN MADATYAN |
| Insulation | 1/8/2026 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 1/8/2026 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 1/30/2026 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 1/30/2026 | Partial Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 5/8/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 5/8/2026 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 5/8/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 5/8/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 5/8/2026 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 5/8/2026 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 6/4/2026 | Approved | ARUTYUN MADATYAN |
| Final | 6/4/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 6/4/2026 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 6/4/2026 | Approved | ARUTYUN MADATYAN |
| Final | 6/11/2026 | OK to Issue CofO | ARUTYUN MADATYAN |