10836 W STAGG ST 91352

Certificate Information: 10836 W STAGG ST 91352

Application / Permit
25010-20000-00347
Plan Check / Job No.
B25VN01900
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1. NEW ADU 1,250 SQ. FT. R.F.A.: 1,140 SQ. FT. (2 STORY)
Permit Issued
Issued on 3/7/2025
Issuing Office
Valley
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 SELLA BENYAMIN
Corrections Issued 2/4/2025 SELLA BENYAMIN
Quality Review Completed 2/5/2025 STEVEN KIM
Building Plans Picked Up 2/10/2025 APPLICANT
Plan Check Approved 2/27/2025 SELLA BENYAMIN
Plan Check Approved 2/27/2025 SELLA BENYAMIN
Issued 3/7/2025 APPLICANT
CofO in Progress 5/6/2026 MATTHEW NELSON
CofO Issued 6/4/2026 RUBEN SALAS
Permit Finaled 6/4/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/10/2025 KEVIN CHUNG
Miscellaneous Cleared 2/10/2025 KEVIN CHUNG
Roof/Waste drainage to street Cleared 2/10/2025 KEVIN CHUNG
Eng Process Fee Ord 176,300 Cleared 2/11/2025 KEVIN CHUNG
Sewer availability Cleared 2/11/2025 KEVIN CHUNG

Contact Information

Contractor Owner-Builder       ,
Engineer Andrejic,, Milos; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/4/2025 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 4/10/2025 Approved MATTHEW NELSON
Deputy Wood Construction 6/18/2025 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 6/25/2025 Approved MATTHEW NELSON
HVAC-Rough 6/25/2025 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 6/25/2025 Approved MATTHEW NELSON
Wood Frame 6/25/2025 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 7/2/2025 Approved MATTHEW NELSON
Green Building Rough 7/2/2025 Approved MATTHEW NELSON
HVAC-Rough 7/2/2025 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 7/2/2025 Approved MATTHEW NELSON
Wood Frame 7/2/2025 Approved MATTHEW NELSON
Insulation 10/30/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/30/2025 Partial Approval MATTHEW NELSON
Drywall Nailing 11/10/2025 Approved LOUIS ESCOTO
Service/Power Release 4/7/2026 Not Ready for Inspection MATTHEW NELSON
Final 4/16/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 4/16/2026 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/16/2026 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/16/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/16/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 4/24/2026 Partial Approval MATTHEW NELSON
Service/Power Release 4/24/2026 Approved MATTHEW NELSON
Final 5/6/2026 OK to Issue CofO MATTHEW NELSON