12993 N EL DORADO AVE 91342
Certificate Information: 12993 N EL DORADO AVE 91342
- Application / Permit
- 25010-20000-00327
- Plan Check / Job No.
- B25VN01848
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ALL ELECTRIC DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/7/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 1/30/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/5/2025 | APPLICANT |
| Applicant returned to address corrections | 2/19/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 3/7/2025 | YAQUB MIRZA |
| Issued | 3/7/2025 | APPLICANT |
| CofO in Progress | 9/11/2025 | KEVIN BERBERYAN |
| Permit Finaled | 9/19/2025 | RUBEN SALAS |
| CofO Issued | 9/19/2025 | RUBEN SALAS |
| Permit Finaled | 9/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2025 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 2/6/2025 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2025 | CARLOS RAMIREZ |
| Miscellaneous | Cleared | 2/10/2025 | ROSALINDA MEZA |
| Sewer availability | Cleared | 2/10/2025 | CARLOS RAMIREZ |
| Grading Pre-Inspection | Cleared | 2/26/2025 | CHARLES POWELL |
| GPI Written Notices | Cleared | 3/7/2025 | LUISANGEL VALENZUELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Morales,, Carlos Alberto; Lic. No.: C69972 | 38100 SAN MATEO AVE PALMDALE, CA 93551 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/28/2025 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/6/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 5/6/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 5/6/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 5/6/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/6/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 5/12/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 5/12/2025 | Not Ready for Inspection | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 5/19/2025 | Approved | LOUIS ESCOTO |
| Green Building Rough | 5/19/2025 | Approved | LOUIS ESCOTO |
| Insulation | 5/19/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 5/19/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 5/22/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 5/27/2025 | Approved | LOUIS ESCOTO |
| Insulation | 8/7/2025 | Partial Inspection | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 8/7/2025 | Partial Inspection | KEVIN BERBERYAN |
| Final | 9/2/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 9/2/2025 | Approved | KEVIN BERBERYAN |
| Green Building Final | 9/2/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV No Gas | KEVIN BERBERYAN |
| Service/Power Release | 9/2/2025 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 9/2/2025 | Approved | KEVIN BERBERYAN |
| Final | 9/5/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 9/5/2025 | Approved | KEVIN BERBERYAN |