1257-1259 W 55TH ST 90037

Certificate Information: 1257-1259 W 55TH ST 90037

Application / Permit
25010-20000-00323
Plan Check / Job No.
B25VN01831
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-STORY DUPLEX W/ ATTACHED 2-CAR GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT) **ePlan**
Permit Issued
Issued on 11/13/2025
Issuing Office
Current Status
CofO Issued on 4/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 NILOOFAR MEHRAIN
Corrections Issued 2/2/2025 NILOOFAR MEHRAIN
Quality Review Completed 2/7/2025 JASON HEALEY
Applicant returned to address corrections 10/16/2025 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/22/2025 NILOOFAR MEHRAIN
Plan Check Approved 11/3/2025 NILOOFAR MEHRAIN
Issued 11/13/2025 APPLICANT
CofO in Progress 4/20/2026 SABAS ALONSO
Permit Finaled 4/23/2026 DEROLD HAUFF
CofO Issued 4/23/2026 DEROLD HAUFF
Permit Finaled 4/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 2/13/2025 MIGUEL ORNELAS
Trees in Parkway Cleared 2/18/2025 BRANDON WONG
Address approval Cleared 2/21/2025 WALLIE JONG
Community Plan Implem. Overlay Cleared 2/21/2025 WALLIE JONG
Hydrant and Access approval Cleared 2/21/2025 KURT CORRAL
Permit Cleared 2/21/2025 WALLIE JONG
Roof/Waste drainage to street Cleared 2/21/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/25/2025 WALLIE JONG
Sewer availability Cleared 3/21/2025 WALLIE JONG
Flood clearance Cleared 4/2/2025 SAMSON WONG
CPC Cleared 9/30/2025 MANERI ROMAN
Community Plan Implem. Overlay Cleared 9/30/2025 MANERI ROMAN
ZI Cleared 9/30/2025 MANERI ROMAN

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/2/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/11/2025 Partial Approval SABAS ALONSO
Underground Mechanical 12/11/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Partial Approval MICHAEL LEWIS
Insulation 12/12/2025 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/15/2026 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 1/30/2026 Corrections Issued SABAS ALONSO
PLUMBING-Rough 1/30/2026 Approved SABAS ALONSO
BUILDING-Rough-Frame 2/2/2026 Partial Approval LUIS CASTRO
Green Building Rough 2/2/2026 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 2/2/2026 Approved LUIS CASTRO
Verify Sprinkler Sign Off 2/2/2026 Approved LUIS CASTRO
BUILDING-Rough-Frame 2/4/2026 Approved ALEX COLIN
Insulation 2/4/2026 Approved ALEX COLIN
Interior/Exterior Lathing 2/4/2026 Partial Approval ALEX COLIN
Drywall Nailing 2/12/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 2/12/2026 Approved SABAS ALONSO
ELECTRICAL-Final 4/10/2026 Approved SABAS ALONSO
HVAC-Final 4/10/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/13/2026 SGSOV Not Ready SALVADOR MARTINEZ
BUILDING-Rough-Frame 4/15/2026 Approved SABAS ALONSO
Final 4/15/2026 OK to Issue CofO SABAS ALONSO
Footing/Foundation/Slab 4/15/2026 Approved SABAS ALONSO
Green Building Final 4/15/2026 Approved SABAS ALONSO
Green Building Rough 4/15/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Approved SABAS ALONSO
Service/Power Release 4/15/2026 Approved SABAS ALONSO
Smoke Detectors 4/15/2026 Approved SABAS ALONSO