16425 W CLYMER ST 91344

Certificate Information: 16425 W CLYMER ST 91344

Application / Permit
25010-20000-00315
Plan Check / Job No.
B25VN01762
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 7/23/2025
Issuing Office
Current Status
Issued on 7/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/30/2025 APPLICANT
Assigned to Plan Check Engineer 2/4/2025 DANIEL YIP
Corrections Issued 2/5/2025 DANIEL YIP
Applicant returned to address corrections 5/15/2025 DANIEL YIP
Plan Check Approved 6/3/2025 DANIEL YIP
Issued 7/23/2025 APPLICANT

Permit Application Clearance Information

Construction within easement Cleared 4/22/2025 GEVORK KARAPETYAN
Address approval Cleared 5/2/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 5/2/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/7/2025 RYAN CASTRO
Sewer availability Cleared 5/7/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/3/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 12/3/2025 Partial Approval CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 12/9/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 12/9/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 12/19/2025 Partial Approval CHRISTOPHER ROJAS
Wood Frame 12/19/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/13/2026 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/13/2026 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 1/13/2026 Approved CHRISTOPHER ROJAS
HVAC-Rough 1/13/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/13/2026 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 1/13/2026 Corrections Issued CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 1/13/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/15/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/15/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 1/15/2026 Approved CHRISTOPHER ROJAS
Wood Frame 1/15/2026 Approved CHRISTOPHER ROJAS
Insulation 1/20/2026 Approved CHRISTOPHER ROJAS
Drywall Nailing 1/22/2026 Approved MICHEL ABAJAN
Shower Pan 1/27/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/29/2026 Partial Approval CHRISTOPHER ROJAS
Interior/Exterior Lathing 2/2/2026 Partial Approval CHRISTOPHER ROJAS
Sewer 4/1/2026 Approved CHRISTOPHER ROJAS
Underground Mechanical 4/1/2026 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 6/3/2026 Partial Approval CHRISTOPHER ROJAS