241-243 E 43RD PL 90011

Certificate Information: 241-243 E 43RD PL 90011

Application / Permit
25010-20000-00310
Plan Check / Job No.
B25VN01721
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan: NEW 2-STORY DUPLEX WITH ATTACHED 2-CAR and 1-CAR GARAGE PER ENGINEER DESIGN
Permit Issued
Issued on 6/24/2025
Issuing Office
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 KAVIAN REFAHI
Corrections Issued 2/1/2025 KAVIAN REFAHI
Quality Review Completed 2/4/2025 CHIHARU SUZUKI
Applicant returned to address corrections 4/22/2025 KAVIAN REFAHI
Applicant returned to address corrections 6/5/2025 KAVIAN REFAHI
Plan Check Approved 6/17/2025 KAVIAN REFAHI
Issued 6/24/2025 APPLICANT
CofO in Progress 12/29/2025 ALEJANDRO DE ARTOLA
Permit Finaled 12/30/2025 DEROLD HAUFF
CofO Issued 12/30/2025 DEROLD HAUFF
Permit Finaled 12/30/2025 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/15/2025 PATRICK PEREZ
Trees in Parkway Cleared 2/18/2025 BRANDON WONG
Address approval Cleared 2/21/2025 DAVID LOPEZ
Low Impact Development (LID) Cleared 2/21/2025 ERNEST TSE
Eng Process Fee Ord 176,300 Cleared 2/25/2025 DAVID LOPEZ
Permit Cleared 2/25/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 2/25/2025 DAVID LOPEZ
Sewer availability Cleared 2/25/2025 DAVID LOPEZ
SB8 RUD Cleared 5/27/2025 NATHANAEL FORAND

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/8/2025 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/8/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 7/15/2025 Approved ALEJANDRO DE ARTOLA
Wood Frame 7/15/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/18/2025 Partial Approval ALEJANDRO DE ARTOLA
Insulation 7/18/2025 Partial Approval ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 7/21/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Partial Approval MICHAEL LEWIS
Deputy Wood Construction 8/8/2025 Conditional Approval RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 8/11/2025 Approved MICHAEL LEWIS
ELECTRICAL-Rough 9/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 9/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/5/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/5/2025 Approved ALEJANDRO DE ARTOLA
Green Building Rough 9/5/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 9/5/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/5/2025 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 9/5/2025 Not Ready for Inspection ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 9/8/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 9/8/2025 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 9/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 9/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/10/2025 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 9/10/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/11/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/12/2025 Approved ALEJANDRO DE ARTOLA
Insulation 9/12/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 9/18/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 9/18/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 12/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/16/2025 Approved ALEJANDRO DE ARTOLA
Final 12/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 12/16/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 12/16/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/16/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Service/Power Release 12/16/2025 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 12/16/2025 Approved ALEJANDRO DE ARTOLA
Final 12/29/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 12/29/2025 Approved ALEJANDRO DE ARTOLA