171-173 W 40TH PL 90037
Certificate Information: 171-173 W 40TH PL 90037
- Application / Permit
- 25010-20000-00309
- Plan Check / Job No.
- B25VN01718
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- eplan: NEW 2-STORY DUPLEX WITH ATTACHED 2-CAR AND 1-CAR GARAGE PER ENGINEER DESIGN
- Permit Issued
- Issued on 7/16/2025
- Issuing Office
- Current Status
- CofO Issued on 2/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | KAVIAN REFAHI |
| Corrections Issued | 2/1/2025 | KAVIAN REFAHI |
| Quality Review Completed | 2/4/2025 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 5/20/2025 | KAVIAN REFAHI |
| Applicant returned to address corrections | 5/29/2025 | KAVIAN REFAHI |
| Plan Check Approved | 6/17/2025 | KAVIAN REFAHI |
| Issued | 7/16/2025 | APPLICANT |
| CofO in Progress | 2/12/2026 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 2/13/2026 | DEROLD HAUFF |
| CofO Issued | 2/13/2026 | DEROLD HAUFF |
| Permit Finaled | 2/13/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/15/2025 | PATRICK PEREZ |
| Address approval | Cleared | 2/21/2025 | TAL SHEMEN |
| Highway dedication | Cleared | 2/21/2025 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 2/25/2025 | TAL SHEMEN |
| SB8 RUD | Cleared | 3/5/2025 | OLIVIA JIN |
| Low Impact Development (LID) | Cleared | 4/16/2025 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 4/17/2025 | TAL SHEMEN |
| Frnt yard landscape/Water mgmt | Cleared | 5/5/2025 | GEORGIA SMITH |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 7/30/2025 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 7/30/2025 | Approved | MICHAEL LEWIS |
| Deputy Reinf. Concrete | 8/1/2025 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 8/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 8/13/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Wood Frame | 8/13/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 8/14/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 9/10/2025 | Conditional Approval | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/20/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/20/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/21/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/21/2025 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/21/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/23/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Insulation | 10/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/3/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 11/10/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 1/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/4/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/4/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/6/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/6/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/6/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/6/2026 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/6/2026 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/6/2026 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 2/6/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/11/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/11/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/11/2026 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 2/11/2026 | Approved | ALEJANDRO DE ARTOLA |