6835 N PENFIELD AVE 91306

Certificate Information: 6835 N PENFIELD AVE 91306

Application / Permit
25010-20000-00287
Plan Check / Job No.
B25VN01565
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: (N) DETACHED ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)3 ALL WORK PER WFPP SEE COMMENTS
Permit Issued
Issued on 4/11/2025
Issuing Office
Current Status
Issued on 4/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/26/2025 APPLICANT
Assigned to Plan Check Engineer 1/29/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 1/30/2025 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 3/20/2025 ALEC MOUSAKHANIAN
Issued 4/11/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/5/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/5/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/5/2025 LEE GUILBEAUX
Sewer availability Cleared 2/5/2025 LEE GUILBEAUX
ZI Cleared 2/5/2025 ASHLEY RODARTE
Public Works-Highway Ded. Cleared 2/5/2025 LEE GUILBEAUX
Construction near power lines Cleared 3/5/2025 GEVORK KARAPETYAN
Construction within easement Cleared 3/5/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/17/2025 Approved ALEXANDER HANDY
Footing/Foundation/Slab 6/17/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 6/17/2025 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 7/7/2025 Not Ready for Inspection ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 7/7/2025 Approved ALEXANDER HANDY
Rough-Elec/Plmb/HVAC 7/7/2025 Corrections Issued ALEXANDER HANDY
Verify Sprinkler Sign Off 7/7/2025 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 7/15/2025 Approved JEFFREY HARTLINE
Green Building Rough 7/15/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 7/15/2025 Partial Approval JEFFREY HARTLINE
Rough-Elec/Plmb/HVAC 7/15/2025 Approved JEFFREY HARTLINE
Shower Pan 7/15/2025 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 7/15/2025 Approved JEFFREY HARTLINE
Insulation 7/21/2025 Approved ALEXANDER HANDY
Drywall Nailing 7/24/2025 Approved KRISTEN CAUSEY
Gas Test 8/21/2025 Approved ALEXANDER HANDY
Final 1/27/2026 Corrections Issued ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 1/27/2026 SGSOV Approved ALEXANDER HANDY
Service/Power Release 1/27/2026 Not Ready for Inspection ALEXANDER HANDY
Smoke Detectors 1/27/2026 Approved ALEXANDER HANDY