4654 N COLUMBUS AVE 91403

Certificate Information: 4654 N COLUMBUS AVE 91403

Application / Permit
25010-20000-00270
Plan Check / Job No.
B25VN01430
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) 18'5"X14'9-1/2" RECREACTION ROOM WITH A HALF BATHROOM. [2 OF 2]
Permit Issued
Issued on 5/28/2025
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2025 APPLICANT
Assigned to Plan Check Engineer 1/23/2025 MARVEL DELACRUZ
Corrections Issued 1/28/2025 MARVEL DELACRUZ
Quality Review Completed 1/30/2025 JASON HEALEY
Building Plans Picked Up 2/6/2025 APPLICANT
Applicant returned to address corrections 3/14/2025 MARVEL DELACRUZ
Plan Check Approved 5/28/2025 MARVEL DELACRUZ
Issued 5/28/2025 APPLICANT
CofO in Progress 10/20/2025 JACK KARGODORIAN
Permit Finaled 11/13/2025 RUBEN SALAS
CofO Issued 11/13/2025 RUBEN SALAS
Permit Finaled 11/13/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/7/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 3/7/2025 BIAINA HARITUNIAN
Sewer availability Cleared 3/7/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 5/16/2025 GEVORK KARAPETYAN
Construction within easement Cleared 5/16/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/30/2025 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 6/17/2025 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 6/20/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 6/30/2025 Corrections Issued JACK KARGODORIAN
Green Building Rough 6/30/2025 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 6/30/2025 Not Ready for Inspection JACK KARGODORIAN
Deputy Wood Construction 7/1/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 7/8/2025 Approved JACK KARGODORIAN
Wood Frame 7/8/2025 Approved JACK KARGODORIAN
Special/Order Compliance 7/10/2025 Partial Inspection JUAN VALENZUELA
HVAC-Rough 7/11/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 7/11/2025 Partial Approval JACK KARGODORIAN
Wood Frame 7/11/2025 Approved JACK KARGODORIAN
Insulation 7/15/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 7/15/2025 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 7/17/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/2/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Drywall Nailing 10/2/2025 Approved CHRISTOPHE COCHRAN
Final 10/2/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 10/2/2025 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 10/2/2025 SGSOV Not Ready CHRISTOPHE COCHRAN
Service/Power Release 10/2/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 10/2/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 10/2/2025 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/7/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 10/7/2025 Not Ready for Inspection MISAEL ESPARZA
Final 10/7/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 10/7/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 10/7/2025 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/7/2025 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 10/7/2025 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 10/7/2025 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 10/9/2025 Approved JACK KARGODORIAN
Final 10/9/2025 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV No Gas JACK KARGODORIAN
Service/Power Release 10/9/2025 Approved JACK KARGODORIAN
Smoke Detectors 10/9/2025 Approved JACK KARGODORIAN
Final 10/20/2025 OK to Issue CofO JACK KARGODORIAN