4654 N COLUMBUS AVE 91403
Certificate Information: 4654 N COLUMBUS AVE 91403
- Application / Permit
- 25010-20000-00270
- Plan Check / Job No.
- B25VN01430
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- (N) 18'5"X14'9-1/2" RECREACTION ROOM WITH A HALF BATHROOM. [2 OF 2]
- Permit Issued
- Issued on 5/28/2025
- Issuing Office
- Current Status
- CofO Issued on 11/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | MARVEL DELACRUZ |
| Corrections Issued | 1/28/2025 | MARVEL DELACRUZ |
| Quality Review Completed | 1/30/2025 | JASON HEALEY |
| Building Plans Picked Up | 2/6/2025 | APPLICANT |
| Applicant returned to address corrections | 3/14/2025 | MARVEL DELACRUZ |
| Plan Check Approved | 5/28/2025 | MARVEL DELACRUZ |
| Issued | 5/28/2025 | APPLICANT |
| CofO in Progress | 10/20/2025 | JACK KARGODORIAN |
| Permit Finaled | 11/13/2025 | RUBEN SALAS |
| CofO Issued | 11/13/2025 | RUBEN SALAS |
| Permit Finaled | 11/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 3/7/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/7/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 5/16/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 5/16/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/30/2025 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 6/17/2025 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 6/20/2025 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/30/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 6/30/2025 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 6/30/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Deputy Wood Construction | 7/1/2025 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 7/8/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 7/8/2025 | Approved | JACK KARGODORIAN |
| Special/Order Compliance | 7/10/2025 | Partial Inspection | JUAN VALENZUELA |
| HVAC-Rough | 7/11/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/11/2025 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 7/11/2025 | Approved | JACK KARGODORIAN |
| Insulation | 7/15/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/15/2025 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/17/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/2/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Drywall Nailing | 10/2/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 10/2/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 10/2/2025 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Service/Power Release | 10/2/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 10/2/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 10/2/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 10/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 10/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 10/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 10/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/7/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 10/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 10/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/9/2025 | Approved | JACK KARGODORIAN |
| Final | 10/9/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV No Gas | JACK KARGODORIAN |
| Service/Power Release | 10/9/2025 | Approved | JACK KARGODORIAN |
| Smoke Detectors | 10/9/2025 | Approved | JACK KARGODORIAN |
| Final | 10/20/2025 | OK to Issue CofO | JACK KARGODORIAN |