9758 N LEMONA AVE 91343

Certificate Information: 9758 N LEMONA AVE 91343

Application / Permit
25010-20000-00245
Plan Check / Job No.
B25VN01294
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED, FULLY ELECTRIC 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER WFPP.
Permit Issued
Issued on 2/11/2025
Issuing Office
Current Status
Issued on 2/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/21/2025 APPLICANT
Assigned to Plan Check Engineer 1/29/2025 HAYATO TSUCHIYA
Corrections Issued 1/30/2025 HAYATO TSUCHIYA
Building Plans Picked Up 1/31/2025 APPLICANT
Issued 2/11/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/10/2025 XOCHITL ARQUIETA
Construction near power lines Cleared 2/10/2025 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/10/2025 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 2/10/2025 XOCHITL ARQUIETA
Sewer availability Cleared 2/10/2025 XOCHITL ARQUIETA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/14/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/14/2025 Partial Approval JENNIFER RABUCHIN
Sewer 3/14/2025 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 3/19/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 4/17/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 7/29/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/25/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Approved JENNIFER RABUCHIN
Gas Test 9/25/2025 Partial Approval JENNIFER RABUCHIN
Green Building Rough 9/25/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 9/25/2025 Approved JENNIFER RABUCHIN
Insulation 9/25/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 9/25/2025 Partial Approval JENNIFER RABUCHIN
Verify Sprinkler Sign Off 9/25/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 10/2/2025 Approved LOUIS ESCOTO
Shower Pan 10/15/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 11/20/2025 Approved JENNIFER RABUCHIN
Pre-Inspection 11/20/2025 Approved JENNIFER RABUCHIN
Underground Mechanical 1/27/2026 Approved JENNIFER RABUCHIN
Final 3/19/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/19/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/19/2026 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 3/19/2026 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 3/19/2026 Approved JENNIFER RABUCHIN
Final 4/9/2026 Corrections Issued MICHEL ABAJAN
Green Building Final 4/9/2026 Not Ready for Inspection MICHEL ABAJAN
Service/Power Release 4/9/2026 Corrections Issued MICHEL ABAJAN
Final 5/12/2026 Not Ready for Inspection JOSE AVILA