8929 N RUBIO AVE 91343
Certificate Information: 8929 N RUBIO AVE 91343
- Application / Permit
- 25010-20000-00243
- Plan Check / Job No.
- B25VN01275
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW DETACHED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1) WITH 2ND FLOOR BALCONY PER ENGINEERING
- Permit Issued
- Issued on 10/16/2025
- Issuing Office
- Current Status
- Issued on 10/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | ALFRED RAMIREZ |
| Corrections Issued | 2/3/2025 | EDWARD MEHRABIAN |
| Quality Review Completed | 2/5/2025 | OMID HEDAYAT |
| Applicant returned to address corrections | 9/2/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 10/9/2025 | ALFRED RAMIREZ |
| Issued | 10/16/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/20/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/20/2025 | BIAINA HARITUNIAN |
| Watercourse | Cleared | 5/20/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/28/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 7/31/2025 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 8/6/2025 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/2/2026 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 2/4/2026 | Partial Approval | GAREN HAYRAPETYAN |
| Special/Order Compliance | 2/4/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 2/9/2026 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2026 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2026 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 4/17/2026 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 4/17/2026 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 4/17/2026 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/22/2026 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 4/22/2026 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 4/22/2026 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 4/22/2026 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 4/22/2026 | Approved | KIRK SANDERS |
| Insulation | 5/4/2026 | Approved | KIRK SANDERS |
| Shower Pan | 5/4/2026 | Approved | KIRK SANDERS |
| Drywall Nailing | 5/11/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/11/2026 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 5/11/2026 | Corrections Issued | MICHEL ABAJAN |
| Underground Mechanical | 5/11/2026 | Approved | MICHEL ABAJAN |