14014-14016 W HUBBARD ST 91342
Certificate Information: 14014-14016 W HUBBARD ST 91342
- Application / Permit
- 25010-20000-00240
- Plan Check / Job No.
- B25VN01249
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN: NEW DETACHED 2-STORY 65'-7" x 46' - 4 7/16" SINGLE FAMILY DWELLING WITH ATTACHED 2ND DWELLING UNIT PER SB9 TWO-UNIT DEVELOPMENT PER ENGINEERING
- Permit Issued
- Issued on 3/26/2025
- Issuing Office
- Current Status
- CofO Issued on 12/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | ALFRED RAMIREZ |
| Corrections Issued | 1/26/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 1/29/2025 | STEVEN KIM |
| Plan Check Approved | 3/25/2025 | ALFRED RAMIREZ |
| No Progress | 3/26/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 3/26/2025 | ALFRED RAMIREZ |
| Issued | 3/26/2025 | APPLICANT |
| CofO in Progress | 11/18/2025 | KEVIN BERBERYAN |
| Permit Finaled | 12/2/2025 | RUBEN SALAS |
| CofO Issued | 12/2/2025 | RUBEN SALAS |
| Permit Finaled | 12/2/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2025 | SAFA JAVANMARDI |
| Address approval | Cleared | 2/6/2025 | SAFA JAVANMARDI |
| Low Impact Development (LID) | Cleared | 2/13/2025 | SARAH YOUSSEF |
| Senate Bill 9 | Cleared | 2/21/2025 | ALEX VELA |
| Hydrant and Access approval | Cleared | 3/6/2025 | PATRICK PEREZ |
| Roof/Waste drainage to street | Cleared | 3/6/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 3/6/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 6047 TAMPA AVE SUITE 304 TARZANA, CA 91356 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/28/2025 | Corrections Issued | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 4/3/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 4/7/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Partial Approval | KEVIN BERBERYAN |
| PLUMBING-Rough | 4/14/2025 | Partial Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2025 | Approved | KEVIN BERBERYAN |
| Deputy Wood Construction | 4/28/2025 | Conditional Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2025 | Partial Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/22/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 5/27/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 5/27/2025 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/28/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 5/28/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 5/28/2025 | Approved | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 5/28/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 6/2/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 6/6/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 6/6/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 8/14/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 8/14/2025 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Final | 8/14/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 8/14/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV No Gas | KEVIN BERBERYAN |
| Smoke Detectors | 8/14/2025 | Approved | KEVIN BERBERYAN |
| Final | 9/17/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 9/17/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 9/17/2025 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 9/17/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 11/18/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Service/Power Release | 11/18/2025 | Not Ready for Inspection | KEVIN BERBERYAN |