14014-14016 W HUBBARD ST 91342

Certificate Information: 14014-14016 W HUBBARD ST 91342

Application / Permit
25010-20000-00240
Plan Check / Job No.
B25VN01249
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN: NEW DETACHED 2-STORY 65'-7" x 46' - 4 7/16" SINGLE FAMILY DWELLING WITH ATTACHED 2ND DWELLING UNIT PER SB9 TWO-UNIT DEVELOPMENT PER ENGINEERING
Permit Issued
Issued on 3/26/2025
Issuing Office
Current Status
CofO Issued on 12/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2025 APPLICANT
Assigned to Plan Check Engineer 1/23/2025 ALFRED RAMIREZ
Corrections Issued 1/26/2025 ALFRED RAMIREZ
Quality Review Completed 1/29/2025 STEVEN KIM
Plan Check Approved 3/25/2025 ALFRED RAMIREZ
No Progress 3/26/2025 ALFRED RAMIREZ
Plan Check Approved 3/26/2025 ALFRED RAMIREZ
Issued 3/26/2025 APPLICANT
CofO in Progress 11/18/2025 KEVIN BERBERYAN
Permit Finaled 12/2/2025 RUBEN SALAS
CofO Issued 12/2/2025 RUBEN SALAS
Permit Finaled 12/2/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/5/2025 SAFA JAVANMARDI
Address approval Cleared 2/6/2025 SAFA JAVANMARDI
Low Impact Development (LID) Cleared 2/13/2025 SARAH YOUSSEF
Senate Bill 9 Cleared 2/21/2025 ALEX VELA
Hydrant and Access approval Cleared 3/6/2025 PATRICK PEREZ
Roof/Waste drainage to street Cleared 3/6/2025 SAFA JAVANMARDI
Sewer availability Cleared 3/6/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 6047 TAMPA AVE   SUITE 304    TARZANA, CA 91356

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/28/2025 Corrections Issued KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 4/3/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 4/7/2025 Corrections Issued GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Partial Approval KEVIN BERBERYAN
PLUMBING-Rough 4/14/2025 Partial Approval KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 4/16/2025 Approved KEVIN BERBERYAN
Deputy Wood Construction 4/28/2025 Conditional Approval KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Partial Approval KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 5/22/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 5/27/2025 Approved KEVIN BERBERYAN
HVAC-Rough 5/27/2025 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 5/28/2025 Approved KEVIN BERBERYAN
HVAC-Rough 5/28/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 5/28/2025 Approved KEVIN BERBERYAN
Verify Sprinkler Sign Off 5/28/2025 Approved KEVIN BERBERYAN
Insulation 6/2/2025 Approved LOUIS ESCOTO
Drywall Nailing 6/6/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 6/6/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 8/14/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 8/14/2025 Corrections Issued KEVIN BERBERYAN
HVAC-Final 8/14/2025 Approved KEVIN BERBERYAN
PLUMBING-Final 8/14/2025 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 8/14/2025 SGSOV No Gas KEVIN BERBERYAN
Smoke Detectors 8/14/2025 Approved KEVIN BERBERYAN
Final 9/17/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 9/17/2025 Approved KEVIN BERBERYAN
PLUMBING-Final 9/17/2025 Approved KEVIN BERBERYAN
Service/Power Release 9/17/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 11/18/2025 OK to Issue CofO KEVIN BERBERYAN
Service/Power Release 11/18/2025 Not Ready for Inspection KEVIN BERBERYAN