13220 W BEAVER ST 91342

Certificate Information: 13220 W BEAVER ST 91342

Application / Permit
25010-20000-00175
Plan Check / Job No.
B25VN00993
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 44'-8" X 25'-4" TWO STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED TRELLIS PATIO
Permit Issued
Issued on 4/9/2025
Issuing Office
Valley
Current Status
CofO Issued on 12/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 SELLA BENYAMIN
Corrections Issued 2/6/2025 SELLA BENYAMIN
Quality Review Completed 2/6/2025 STEVEN KIM
Building Plans Picked Up 2/12/2025 APPLICANT
Plan Check Approved 4/1/2025 SELLA BENYAMIN
Issued 4/9/2025 APPLICANT
CofO in Progress 12/12/2025 KEVIN BERBERYAN
Permit Finaled 12/31/2025 RUBEN SALAS
CofO Issued 12/31/2025 RUBEN SALAS
Permit Finaled 12/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/1/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 3/1/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 3/4/2025 SAFA JAVANMARDI
Sewer availability Cleared 3/4/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/6/2025 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 5/12/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 5/15/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 6/2/2025 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 6/2/2025 Corrections Issued RAUL OLAGI
PLUMBING-Rough 6/2/2025 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 7/9/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 7/9/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 7/9/2025 Conditional Approval KEVIN BERBERYAN
Underground Mechanical 7/9/2025 Conditional Approval KEVIN BERBERYAN
Interior/Exterior Lathing 7/21/2025 Approved KEVIN BERBERYAN
Insulation 7/24/2025 Corrections Issued MICHAEL CORTEZ
BUILDING-Rough-Frame 7/31/2025 Approved KEVIN BERBERYAN
Green Building Rough 7/31/2025 Approved KEVIN BERBERYAN
Insulation 7/31/2025 Approved KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 7/31/2025 Approved KEVIN BERBERYAN
Drywall Nailing 8/5/2025 Approved KEVIN BERBERYAN
Final 11/13/2025 Corrections Issued KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 11/13/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 11/13/2025 Approved KEVIN BERBERYAN
Final 12/2/2025 Partial Approval KEVIN BERBERYAN
Green Building Final 12/2/2025 Approved KEVIN BERBERYAN
Service/Power Release 12/2/2025 Approved KEVIN BERBERYAN
Final 12/12/2025 OK to Issue CofO KEVIN BERBERYAN