20502 W LULL ST 91306

Certificate Information: 20502 W LULL ST 91306

Application / Permit
25010-20000-00169
Plan Check / Job No.
B25VN00914
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW 24' X 35'-9" 1-STORY ACCESSORY DWELLING UNIT PER GC 66323(a)(2). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/11/2025
Issuing Office
Current Status
CofO Issued on 5/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 RAPHAEL ROSAS
Corrections Issued 2/4/2025 RAPHAEL ROSAS
Quality Review Completed 2/4/2025 STEVEN KIM
Plan Check Approved 4/10/2025 RAPHAEL ROSAS
Issued 4/11/2025 APPLICANT
CofO in Progress 5/29/2026 ALEXANDER HANDY
Permit Finaled 5/29/2026 JOHN JANSON
CofO Issued 5/29/2026 JOHN JANSON
Permit Finaled 5/29/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/18/2025 BIAINA HARITUNIAN
Miscellaneous Cleared 3/18/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 3/18/2025 BIAINA HARITUNIAN
Work Adjacent to Public Way Cleared 3/18/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 3/26/2025 GEVORK KARAPETYAN
Eng Process Fee Ord 176,300 Cleared 3/26/2025 BIAINA HARITUNIAN
Sewer availability Cleared 3/26/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/9/2025 Partial Approval ALEXANDER HANDY
Footing/Foundation/Slab 9/15/2025 Approved ALEXANDER HANDY
Special/Order Compliance 9/15/2025 Partial Approval SCOTT SOBEL
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Partial Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 10/15/2025 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 10/15/2025 Approved ALEXANDER HANDY
Shower Pan 10/16/2025 Approved TROY SANDERS
BUILDING-Rough-Frame 10/21/2025 Approved ALEXANDER HANDY
ELECTRICAL-Rough 10/21/2025 Approved ALEXANDER HANDY
Green Building Rough 10/21/2025 Approved ALEXANDER HANDY
HVAC-Rough 10/21/2025 Approved ALEXANDER HANDY
Verify Sprinkler Sign Off 10/21/2025 Approved ALEXANDER HANDY
Insulation 10/24/2025 Conditional Approval ALEXANDER HANDY
Interior/Exterior Lathing 10/24/2025 Partial Approval ALEXANDER HANDY
Drywall Nailing 10/28/2025 Approved TROY SANDERS
Interior/Exterior Lathing 11/3/2025 Approved KRISTEN CAUSEY
Sewer 11/6/2025 Approved TROY SANDERS
Underground Mechanical 11/6/2025 Partial Approval TROY SANDERS
Final 4/6/2026 Partial Inspection ALEXANDER HANDY
Green Building Final 4/6/2026 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 4/6/2026 SGSOV No Gas ALEXANDER HANDY
Service/Power Release 4/6/2026 Not Required ALEXANDER HANDY
Smoke Detectors 4/6/2026 Approved ALEXANDER HANDY
Final 5/29/2026 OK to Issue CofO ALEXANDER HANDY