17048 W CALAHAN ST 91325

Certificate Information: 17048 W CALAHAN ST 91325

Application / Permit
25010-20000-00155
Plan Check / Job No.
B25VN00785
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW DETACHED ADU PER GC 66323(a)(2). ALL WORK PER ENG.
Permit Issued
Issued on 2/20/2025
Issuing Office
Current Status
CofO Issued on 5/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2025 APPLICANT
Assigned to Plan Check Engineer 1/17/2025 LUISANGEL VALENZUELA
Corrections Issued 1/17/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/12/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/15/2025 LUISANGEL VALENZUELA
Plan Check Approved 2/19/2025 LUISANGEL VALENZUELA
Issued 2/20/2025 APPLICANT
CofO in Progress 10/2/2025 NICHOLAS TROWBRIDGE
CofO in Progress 2/13/2026 CHRISTOPHER ROJAS
No Progress 2/27/2026 JOSE AVILA
CofO in Progress 2/27/2026 JOSE AVILA
CofO Issued 5/7/2026 RUBEN SALAS
Permit Finaled 5/7/2026 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/22/2025 CHARLES POWELL
Address approval Cleared 1/23/2025 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 1/23/2025 CARLOS RAMIREZ
ZA Case Cleared 1/24/2025 DALIA MOKAYED
Sewer availability Cleared 1/27/2025 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/10/2025 CARLOS RAMIREZ
GPI Written Notices Cleared 2/19/2025 LUISANGEL VALENZUELA

Contact Information

Contractor Pacific Point Builders Inc; Lic. No.: 768984-B       ,
Engineer Mohammadi,, Saeid; Lic. No.: NA82330       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/4/2025 No Access for Inspection ROBERT GOLD
PLUMBING-Rough 3/20/2025 Partial Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 3/25/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/25/2025 Partial Inspection CHRISTOPHER ROJAS
Underground Mechanical 3/25/2025 Approved CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 3/27/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/27/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/18/2025 Corrections Issued CHRISTOPHER ROJAS
Sewer 4/18/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 4/18/2025 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/24/2025 Partial Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 4/24/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/23/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 5/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 5/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 5/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 5/23/2025 Approved CHRISTOPHER ROJAS
Wood Frame 5/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/30/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 5/30/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 5/30/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 5/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Shower Pan 5/30/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 6/11/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 6/24/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 6/24/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 6/24/2025 Partial Approval NICHOLAS TROWBRIDGE
Insulation 6/26/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 7/1/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 7/1/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 7/3/2025 Corrections Issued MICHAEL CORTEZ
Final 9/12/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 9/12/2025 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Not Required NICHOLAS TROWBRIDGE
Service/Power Release 9/12/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Smoke Detectors 9/12/2025 Approved NICHOLAS TROWBRIDGE
Final 9/22/2025 Corrections Issued NICHOLAS TROWBRIDGE
Service/Power Release 9/22/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 9/26/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Service/Power Release 9/26/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 10/1/2025 OK to Issue CofO NICHOLAS TROWBRIDGE
Service/Power Release 10/1/2025 Approved NICHOLAS TROWBRIDGE
Special/Order Compliance 10/2/2025 Corrections Issued NICHOLAS TROWBRIDGE
Final 2/13/2026 OK to Issue CofO CHRISTOPHER ROJAS