4698-4700 N KRAFT AVE 91602
Certificate Information: 4698-4700 N KRAFT AVE 91602
- Application / Permit
- 25010-20000-00153
- Plan Check / Job No.
- B25VN00742
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW FULLY SPRINKLERED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) AND SECOND DWELLING UNIT ABOVE PER SB 9
- Permit Issued
- Issued on 9/19/2025
- Issuing Office
- Current Status
- Issued on 9/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 1/18/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/22/2025 | APPLICANT |
| Applicant returned to address corrections | 9/11/2025 | JEROME MAGAT PALMA |
| Plan Check Approved | 9/18/2025 | JEROME MAGAT PALMA |
| Issued | 9/19/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2025 | BRYAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 5/14/2025 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2025 | BRYAN GODINEZ |
| Miscellaneous | Cleared | 5/20/2025 | JACQUELINE TORRES |
| Sewer availability | Cleared | 5/20/2025 | BRYAN GODINEZ |
| Miscellaneous | Cleared | 5/22/2025 | MIGUEL CRISOSTOMO |
| Specific Plan | Cleared | 5/27/2025 | SASHA KASSAB |
| Senate Bill 9 | Cleared | 5/28/2025 | JOANNA MARROQUIN |
| Hydrant and Access approval | Cleared | 6/3/2025 | LAVEON RIDER |
| Construction near power lines | Cleared | 9/18/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/6/2025 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 11/12/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 11/12/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2025 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 12/11/2025 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/30/2026 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/30/2026 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2026 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 1/30/2026 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/6/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/6/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/6/2026 | Approved | JAVIER RAMOS JR |
| Insulation | 2/19/2026 | Partial Approval | MICHAEL CORTEZ |
| Shower Pan | 2/19/2026 | Approved | MICHAEL CORTEZ |
| Deputy Steel/Welding | 2/20/2026 | Conditional Approval | RAUL OLAGI |
| Interior/Exterior Lathing | 2/24/2026 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 3/2/2026 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 3/2/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 3/31/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Sewer | 3/31/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/15/2026 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 4/15/2026 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 4/15/2026 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 4/15/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/28/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 4/28/2026 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 4/28/2026 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/28/2026 | SGSOV Not Required | JAVIER RAMOS JR |
| Service/Power Release | 5/8/2026 | Approved | JAVIER RAMOS JR |
| Final | 7/22/2026 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 7/22/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 7/22/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 7/22/2026 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 7/22/2026 | Approved | JAVIER RAMOS JR |