8315 N NATALIE LANE 91304

Certificate Information: 8315 N NATALIE LANE 91304

Application / Permit
25010-20000-00146
Plan Check / Job No.
B25VN00678
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW DETACHED IRR.-SHAPED ACCESSORY DWELLING UNIT PER GCS 66323(A)(2)
Permit Issued
Issued on 2/19/2025
Issuing Office
Current Status
CofO Issued on 10/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2025 APPLICANT
Assigned to Plan Check Engineer 1/17/2025 GURUNATH NESARAJAH
Corrections Issued 1/18/2025 GURUNATH NESARAJAH
Plan Check Approved 2/13/2025 PINANK PATEL
Issued 2/19/2025 APPLICANT
CofO in Progress 9/30/2025 JEFFREY HARTLINE
Permit Finaled 10/2/2025 JOHN JANSON
CofO Issued 10/2/2025 JOHN JANSON
Permit Finaled 10/2/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/24/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/24/2025 LEE GUILBEAUX
ZA Case Cleared 1/24/2025 DORIAN AGUILAR
Public Works-Highway Ded. Cleared 1/24/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/27/2025 LEE GUILBEAUX
Sewer availability Cleared 1/27/2025 LEE GUILBEAUX
Grading Pre-Inspection Cleared 1/27/2025 CHARLES POWELL
GPI Written Notices Cleared 2/13/2025 GURUNATH NESARAJAH

Contact Information

Contractor Flip It Homes Inc; Lic. No.: 1043456-B       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 4/3/2025 Corrections Issued JEFFREY HARTLINE
Underground Mechanical 4/3/2025 Partial Approval JEFFREY HARTLINE
Footing/Foundation/Slab 4/14/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Partial Approval JEFFREY HARTLINE
Pre-Inspection 5/20/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/29/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 5/29/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Partial Approval JEFFREY HARTLINE
Green Building Rough 5/29/2025 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 5/29/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 5/29/2025 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 5/29/2025 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 6/3/2025 Approved JEFFREY HARTLINE
Green Building Rough 6/3/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 6/3/2025 Partial Approval JEFFREY HARTLINE
Sewer 6/3/2025 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 6/3/2025 Approved JEFFREY HARTLINE
Insulation 6/9/2025 Approved JEFFREY HARTLINE
Drywall Nailing 6/16/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 6/17/2025 Not Ready for Inspection JEFFREY HARTLINE
Shower Pan 6/17/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 6/23/2025 Partial Approval ARUTYUN MADATYAN
ELECTRICAL-Final 9/12/2025 Approved JEFFREY HARTLINE
Final 9/12/2025 Corrections Issued JEFFREY HARTLINE
Green Building Final 9/12/2025 Approved JEFFREY HARTLINE
HVAC-Final 9/12/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 9/12/2025 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Not Ready JEFFREY HARTLINE
Service/Power Release 9/12/2025 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 9/12/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 9/16/2025 Approved JEFFREY HARTLINE
Final 9/16/2025 OK to Issue CofO JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 9/16/2025 SGSOV Approved JEFFREY HARTLINE
Service/Power Release 9/16/2025 Approved JEFFREY HARTLINE