8315 N NATALIE LANE 91304
Certificate Information: 8315 N NATALIE LANE 91304
- Application / Permit
- 25010-20000-00146
- Plan Check / Job No.
- B25VN00678
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW DETACHED IRR.-SHAPED ACCESSORY DWELLING UNIT PER GCS 66323(A)(2)
- Permit Issued
- Issued on 2/19/2025
- Issuing Office
- Current Status
- CofO Issued on 10/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2025 | GURUNATH NESARAJAH |
| Corrections Issued | 1/18/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/13/2025 | PINANK PATEL |
| Issued | 2/19/2025 | APPLICANT |
| CofO in Progress | 9/30/2025 | JEFFREY HARTLINE |
| Permit Finaled | 10/2/2025 | JOHN JANSON |
| CofO Issued | 10/2/2025 | JOHN JANSON |
| Permit Finaled | 10/2/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/24/2025 | LEE GUILBEAUX |
| ZA Case | Cleared | 1/24/2025 | DORIAN AGUILAR |
| Public Works-Highway Ded. | Cleared | 1/24/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/27/2025 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 1/27/2025 | CHARLES POWELL |
| GPI Written Notices | Cleared | 2/13/2025 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 4/3/2025 | Corrections Issued | JEFFREY HARTLINE |
| Underground Mechanical | 4/3/2025 | Partial Approval | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 4/14/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Partial Approval | JEFFREY HARTLINE |
| Pre-Inspection | 5/20/2025 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/29/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 5/29/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2025 | Partial Approval | JEFFREY HARTLINE |
| Green Building Rough | 5/29/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Rough | 5/29/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 5/29/2025 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 5/29/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 6/3/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 6/3/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 6/3/2025 | Partial Approval | JEFFREY HARTLINE |
| Sewer | 6/3/2025 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 6/3/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 6/9/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 6/16/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 6/17/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Shower Pan | 6/17/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 6/23/2025 | Partial Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 9/12/2025 | Approved | JEFFREY HARTLINE |
| Final | 9/12/2025 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 9/12/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 9/12/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 9/12/2025 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 9/12/2025 | SGSOV Not Ready | JEFFREY HARTLINE |
| Service/Power Release | 9/12/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 9/12/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 9/16/2025 | Approved | JEFFREY HARTLINE |
| Final | 9/16/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 9/16/2025 | SGSOV Approved | JEFFREY HARTLINE |
| Service/Power Release | 9/16/2025 | Approved | JEFFREY HARTLINE |