17422 W DONMETZ ST 91344
Certificate Information: 17422 W DONMETZ ST 91344
- Application / Permit
- 25010-20000-00138
- Plan Check / Job No.
- B25VN00652
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRR.-SHAPE DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 5/29/2025
- Issuing Office
- Current Status
- CofO Issued on 2/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2025 | GURUNATH NESARAJAH |
| Corrections Issued | 1/16/2025 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 2/3/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/28/2025 | MADISON O'DELL |
| Issued | 5/29/2025 | APPLICANT |
| CofO in Progress | 12/15/2025 | STEVEN BACK |
| CofO in Progress | 1/27/2026 | STEVEN BACK |
| CofO in Progress | 2/20/2026 | STEVEN BACK |
| Permit Finaled | 2/20/2026 | JOHN JANSON |
| CofO Issued | 2/20/2026 | JOHN JANSON |
| Permit Finaled | 2/20/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/16/2025 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 1/16/2025 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2025 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 1/21/2025 | WALTER RAMIREZ |
| Private sewage disp. approval | Cleared | 5/21/2025 | MICHAEL TEMPLE |
| Grading Pre-Inspection | Cleared | 5/27/2025 | MADISON O'DELL |
Contact Information
| Contractor | Pnr Builders Inc; Lic. No.: 1028148-B | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/25/2025 | Partial Approval | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 7/2/2025 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 7/2/2025 | Approved | STEVEN BACK |
| Deputy Wood Construction | 7/18/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2025 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 8/7/2025 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 8/7/2025 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 8/7/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 8/15/2025 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 8/19/2025 | Approved | STEVEN BACK |
| Green Building Rough | 8/19/2025 | Approved | STEVEN BACK |
| Insulation | 8/19/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 8/26/2025 | Approved | JEFFREY PARD |
| Shower Pan | 8/26/2025 | Approved | JEFFREY PARD |
| Sewer | 11/3/2025 | Approved | KRISTEN CAUSEY |
| Underground Mechanical | 11/5/2025 | Approved | STEVEN BACK |
| Final | 12/8/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 12/8/2025 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 12/8/2025 | Corrections Issued | STEVEN BACK |
| Final | 12/15/2025 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 12/15/2025 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 12/15/2025 | Approved | STEVEN BACK |
| Smoke Detectors | 12/15/2025 | Approved | STEVEN BACK |
| Final | 1/27/2026 | Corrections Issued | STEVEN BACK |
| Final | 2/20/2026 | OK to Issue CofO | STEVEN BACK |