220 E 83RD ST 90003

Certificate Information: 220 E 83RD ST 90003

Application / Permit
25010-20000-00131
Plan Check / Job No.
B25VN00622
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1).
Permit Issued
Issued on 4/15/2025
Issuing Office
Current Status
CofO in Progress on 6/4/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/15/2025 APPLICANT
Assigned to Plan Check Engineer 1/17/2025 GIOVANNY CHAVEZ
Corrections Issued 1/18/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 3/20/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 3/29/2025 GIOVANNY CHAVEZ
Plan Check Approved 4/9/2025 GIOVANNY CHAVEZ
Issued 4/15/2025 APPLICANT
CofO in Progress 6/2/2026 JOHN QUINTANILLA
No Progress 6/4/2026 DEROLD HAUFF
CofO in Progress 6/4/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/29/2025 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 1/29/2025 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 2/4/2025 CHRISTINA BRACO
Sewer availability Cleared 2/4/2025 CHRISTINA BRACO
Construction near power lines Cleared 3/12/2025 RIDWAN HARDY

Contact Information

Contractor Over The Top Property Preservation Llc; Lic. No.: 1103342-B       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 1543      HAWTHORNE, CA 90251

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/19/2025 Approved MICHAEL LEWIS
Sewer 6/20/2025 Approved LUIS CASTRO
Underground Mechanical 6/20/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 6/25/2025 Corrections Issued JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 6/27/2025 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 7/21/2025 Not Ready for Inspection JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 7/21/2025 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 7/21/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 7/21/2025 Not Ready for Inspection JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Corrections Issued JOHN QUINTANILLA
Green Building Final 7/23/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 7/23/2025 Partial Approval JOHN QUINTANILLA
BUILDING-Rough-Frame 7/25/2025 Partial Approval WAYNE REGESTER
Green Building Rough 7/25/2025 Not Ready for Inspection WAYNE REGESTER
PLUMBING-Rough 7/25/2025 Partial Approval WAYNE REGESTER
Verify Sprinkler Sign Off 7/25/2025 Approved WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Not Ready for Inspection BARRY HACHE
Insulation 7/30/2025 Partial Approval BARRY HACHE
BUILDING-Rough-Frame 8/1/2025 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Partial Approval LUIS CASTRO
Green Building Rough 8/1/2025 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 8/21/2025 Approved WAYNE REGESTER
Wood Frame 8/21/2025 Not Ready for Inspection WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 8/26/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 8/26/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 8/29/2025 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Drilled-In Anchors 9/2/2025 Completed (special insp) RONNIE MEDINA
Deputy Reinf. Concrete 9/2/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 9/3/2025 Corrections Issued JOHN QUINTANILLA
HVAC-Rough 9/3/2025 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 9/16/2025 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 9/16/2025 Approved SABAS ALONSO
Green Building Rough 9/16/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 9/16/2025 Approved SABAS ALONSO
Green Building Final 9/23/2025 Not Ready for Inspection JOHN QUINTANILLA
Service/Power Release 9/23/2025 Not Ready for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 9/24/2025 Corrections Issued JOHN QUINTANILLA
Green Building Rough 9/24/2025 Not Ready for Inspection JOHN QUINTANILLA
Interior/Exterior Lathing 9/24/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 9/24/2025 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 9/29/2025 Approved JOHN QUINTANILLA
Green Building Rough 9/29/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 9/29/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 9/29/2025 Approved JOHN QUINTANILLA
Insulation 10/7/2025 Approved JOHN QUINTANILLA
Drywall Nailing 10/14/2025 Corrections Issued JOHN QUINTANILLA
Drywall Nailing 10/17/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 10/17/2025 Approved ANTHONY RAMOS
Service/Power Release 11/6/2025 Not Ready for Inspection JOHN QUINTANILLA
Service/Power Release 11/19/2025 Corrections Issued JOHN QUINTANILLA
Pre-Inspection 11/25/2025 Partial Inspection JOHN QUINTANILLA
ELECTRICAL-Final 11/26/2025 Approved JOHN QUINTANILLA
Service/Power Release 11/26/2025 Approved JOHN QUINTANILLA
Final 4/27/2026 Partial Approval JOHN QUINTANILLA
Green Building Final 4/27/2026 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 4/27/2026 SGSOV Not Required JOHN QUINTANILLA
Smoke Detectors 4/27/2026 Approved JOHN QUINTANILLA
Final 4/30/2026 Partial Approval JOHN QUINTANILLA
Final 6/1/2026 OK to Issue CofO JOHN QUINTANILLA