10649 W TUXFORD ST 91352

Certificate Information: 10649 W TUXFORD ST 91352

Application / Permit
25010-20000-00118
Plan Check / Job No.
B25VN00531
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW 20' X 30' 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/8/2025
Issuing Office
Current Status
Issued on 9/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/9/2025 APPLICANT
Assigned to Plan Check Engineer 1/23/2025 RAPHAEL ROSAS
Corrections Issued 1/28/2025 RAPHAEL ROSAS
Quality Review Completed 1/31/2025 STEVEN KIM
Applicant returned to address corrections 4/1/2025 RAPHAEL ROSAS
Plan Check Approved 5/2/2025 RAPHAEL ROSAS
Issued 9/8/2025 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 1/31/2025 JASON CHAN
ZA Case Cleared 1/31/2025 JASON CHAN
Address approval Cleared 2/4/2025 EDGAR ALCARAZ
BHO/Hillside ordinance Cleared 2/4/2025 EDGAR ALCARAZ
BHO/Hillside ordinance Cleared 2/4/2025 EDGAR ALCARAZ
BHO/Hillside ordinance Cleared 2/4/2025 EDGAR ALCARAZ
BHO/Hillside ordinance Cleared 2/4/2025 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 2/4/2025 EDGAR ALCARAZ
Specific Plan Cleared 2/4/2025 ERICK MARCHENA
ZI Cleared 2/4/2025 ERICK MARCHENA
Eng Process Fee Ord 176,300 Cleared 2/5/2025 EDGAR ALCARAZ
Distance to fire station Cleared 3/6/2025 FRANK GOMEZ
Hydrant and Access approval Cleared 3/6/2025 FRANK GOMEZ
Private sewage disp. approval Cleared 4/21/2025 MICHAEL TEMPLE
GPI Written Notices Cleared 5/2/2025 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 5/2/2025 GERMAN RODRIGUEZ MENDOZA

Contact Information

Contractor Owner-Builder       ,
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/17/2025 Partial Inspection DAVID ANDERSON
PLUMBING-Rough 10/21/2025 Partial Approval DAVID ANDERSON
Footing/Foundation/Slab 10/24/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/11/2026 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 3/12/2026 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/9/2026 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 4/14/2026 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 4/14/2026 Approved DAVID ANDERSON
Green Building Rough 4/14/2026 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 4/14/2026 Corrections Issued DAVID ANDERSON
Verify Sprinkler Sign Off 4/14/2026 Approved DAVID ANDERSON
ELECTRICAL-Rough 4/22/2026 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/22/2026 Corrections Issued DAVID ANDERSON
Green Building Rough 4/22/2026 Not Ready for Inspection DAVID ANDERSON
Verify Sprinkler Sign Off 4/22/2026 Approved DAVID ANDERSON
BUILDING-Rough-Frame 5/5/2026 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 5/5/2026 Not Ready for Inspection DAVID ANDERSON
Green Building Rough 5/5/2026 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 5/13/2026 Approved DAVID ANDERSON
PLUMBING-Rough 5/13/2026 Approved DAVID ANDERSON
BUILDING-Rough-Frame 6/15/2026 Partial Approval DAVID ANDERSON
HVAC-Rough 6/15/2026 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 6/22/2026 Approved DAVID ANDERSON
Green Building Rough 6/22/2026 Approved DAVID ANDERSON
HVAC-Rough 6/22/2026 Approved DAVID ANDERSON
Insulation 6/22/2026 Approved DAVID ANDERSON
Drywall Nailing 7/7/2026 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/7/2026 Partial Approval MATTHEW NELSON