20536 W ENADIA WAY 91306

Certificate Information: 20536 W ENADIA WAY 91306

Application / Permit
25010-20000-00113
Plan Check / Job No.
B25VN00502
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: NEW 2-STORY 2ND DWELLING UNIT PER SB9 TWO-UNIT DEVELOPMENT WITH FRONT PATIO COVER PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 5/15/2025
Issuing Office
Current Status
CofO in Progress on 5/20/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/9/2025 APPLICANT
Assigned to Plan Check Engineer 1/16/2025 ALFRED RAMIREZ
Corrections Issued 1/18/2025 ALFRED RAMIREZ
Quality Review Completed 1/23/2025 STEVEN KIM
Applicant returned to address corrections 3/7/2025 ALFRED RAMIREZ
Applicant returned to address corrections 3/21/2025 ALFRED RAMIREZ
Applicant returned to address corrections 4/16/2025 ALFRED RAMIREZ
Plan Check Approved 5/14/2025 ALFRED RAMIREZ
Issued 5/15/2025 APPLICANT
CofO in Progress 4/29/2026 ALEXANDER HANDY
No Progress 5/20/2026 ROBERT GOLD
CofO in Progress 5/20/2026 ROBERT GOLD

Permit Application Clearance Information

Address approval Cleared 1/22/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/23/2025 BIAINA HARITUNIAN
Sewer availability Cleared 1/23/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 3/10/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/10/2025 LEE GUILBEAUX
Hydrant and Access approval Cleared 3/11/2025 JOHN CONNEALLY
Senate Bill 9 Cleared 3/28/2025 DANIEL CORONADO

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Partial Approval ALEXANDER HANDY
Footing/Foundation/Slab 5/22/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 5/22/2025 Partial Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 Partial Inspection KRISTEN CAUSEY
ELECTRICAL-Rough 6/17/2025 Corrections Issued ALEXANDER HANDY
PLUMBING-Rough 6/23/2025 Not Ready for Inspection SCOTT SOBEL
Wood Frame 6/23/2025 Not Ready for Inspection SCOTT SOBEL
BUILDING-Rough-Frame 6/26/2025 Corrections Issued SCOTT SOBEL
HVAC-Rough 6/26/2025 Not Ready for Inspection SCOTT SOBEL
BUILDING-Rough-Frame 7/9/2025 Conditional Approval ALEXANDER HANDY
ELECTRICAL-Rough 7/9/2025 Approved ALEXANDER HANDY
Green Building Rough 7/9/2025 Approved ALEXANDER HANDY
HVAC-Rough 7/9/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 7/9/2025 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 7/9/2025 Approved ALEXANDER HANDY
Verify Sprinkler Sign Off 7/9/2025 Approved ALEXANDER HANDY
Insulation 7/14/2025 Not Ready for Inspection SCOTT SOBEL
Insulation 7/17/2025 Approved ALEXANDER HANDY
Drywall Nailing 7/21/2025 Approved ALEXANDER HANDY
Underground Mechanical 10/10/2025 Not Ready for Inspection SEAN WIRCH
BUILDING-Rough-Frame 10/22/2025 Approved ALEXANDER HANDY
Drywall Nailing 10/22/2025 Approved ALEXANDER HANDY
Final 10/22/2025 Corrections Issued ALEXANDER HANDY
Green Building Final 10/22/2025 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 10/22/2025 SGSOV No Gas ALEXANDER HANDY
Service/Power Release 10/22/2025 Not Ready for Inspection ALEXANDER HANDY
Smoke Detectors 10/22/2025 Approved ALEXANDER HANDY
Final 12/11/2025 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 12/11/2025 Not Ready for Inspection GEVORK IPCHYAN
Service/Power Release 12/11/2025 Not Ready for Inspection GEVORK IPCHYAN
Final 1/26/2026 Not Ready for Inspection TROY SANDERS
Green Building Final 1/26/2026 Approved TROY SANDERS
Service/Power Release 1/26/2026 Not Ready for Inspection TROY SANDERS
ELECTRICAL-Final 2/17/2026 Approved ALEXANDER HANDY
Final 2/17/2026 Partial Inspection ALEXANDER HANDY
HVAC-Final 2/17/2026 Approved ALEXANDER HANDY
PLUMBING-Final 2/17/2026 Approved ALEXANDER HANDY
Service/Power Release 2/17/2026 Not Required ALEXANDER HANDY
Final 4/29/2026 OK to Issue CofO ALEXANDER HANDY
Special/Order Compliance 5/20/2026 Corrections Issued ALEXANDER HANDY