20538 W ENADIA WAY 91306
Certificate Information: 20538 W ENADIA WAY 91306
- Application / Permit
- 25010-20000-00112
- Plan Check / Job No.
- B25VN00501
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* NEW 20' X 30' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 4/23/2025
- Issuing Office
- Current Status
- CofO Issued on 5/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | SELLA BENYAMIN |
| Corrections Issued | 1/21/2025 | SELLA BENYAMIN |
| Quality Review Completed | 1/23/2025 | STEVEN KIM |
| Applicant returned to address corrections | 3/6/2025 | SELLA BENYAMIN |
| Applicant returned to address corrections | 3/14/2025 | SELLA BENYAMIN |
| Plan Check Approved | 4/18/2025 | SELLA BENYAMIN |
| Issued | 4/23/2025 | APPLICANT |
| CofO in Progress | 4/29/2026 | ALEXANDER HANDY |
| Permit Finaled | 5/26/2026 | JOHN JANSON |
| Permit Finaled | 5/26/2026 | JOHN JANSON |
| CofO Issued | 5/26/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/22/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 1/23/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 3/10/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/10/2025 | LEE GUILBEAUX |
| ZI | Cleared | 3/28/2025 | DANIEL CORONADO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/30/2025 | Partial Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 5/8/2025 | Partial Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 5/12/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 5/15/2025 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Partial Inspection | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 6/17/2025 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 6/23/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Wood Frame | 6/23/2025 | Not Ready for Inspection | SCOTT SOBEL |
| BUILDING-Rough-Frame | 6/26/2025 | Corrections Issued | SCOTT SOBEL |
| HVAC-Rough | 6/26/2025 | Not Ready for Inspection | SCOTT SOBEL |
| BUILDING-Rough-Frame | 7/9/2025 | Corrections Issued | ALEXANDER HANDY |
| Interior/Exterior Lathing | 7/9/2025 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 7/31/2025 | Approved | SCOTT SOBEL |
| Green Building Rough | 7/31/2025 | Approved | SCOTT SOBEL |
| Insulation | 7/31/2025 | Approved | SCOTT SOBEL |
| Special/Order Compliance | 7/31/2025 | Approved | ROBERT GOLD |
| Verify Sprinkler Sign Off | 7/31/2025 | Approved | SCOTT SOBEL |
| Drywall Nailing | 8/4/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Drywall Nailing | 8/8/2025 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 10/10/2025 | Not Ready for Inspection | SEAN WIRCH |
| Final | 10/22/2025 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 10/22/2025 | SGSOV No Gas | ALEXANDER HANDY |
| Service/Power Release | 10/22/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Smoke Detectors | 10/22/2025 | Approved | ALEXANDER HANDY |
| Final | 12/11/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Service/Power Release | 12/11/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 1/26/2026 | Not Ready for Inspection | TROY SANDERS |
| Service/Power Release | 1/26/2026 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Final | 2/17/2026 | Approved | ALEXANDER HANDY |
| Final | 2/17/2026 | Partial Inspection | ALEXANDER HANDY |
| HVAC-Final | 2/17/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 2/17/2026 | Approved | ALEXANDER HANDY |
| Service/Power Release | 2/17/2026 | Not Required | ALEXANDER HANDY |
| Final | 4/29/2026 | OK to Issue CofO | ALEXANDER HANDY |