6861-6861 1/2 N ATOLL AVE 91605
Certificate Information: 6861-6861 1/2 N ATOLL AVE 91605
- Application / Permit
- 25010-20000-00068
- Plan Check / Job No.
- B25VN00298
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40' X 20' TWO STORY (2) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d), and (g)
- Permit Issued
- Issued on 2/13/2025
- Issuing Office
- Current Status
- CofO Issued on 11/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | SELLA BENYAMIN |
| Corrections Issued | 1/23/2025 | SELLA BENYAMIN |
| Quality Review Completed | 1/24/2025 | STEVEN KIM |
| Building Plans Picked Up | 1/30/2025 | APPLICANT |
| Plan Check Approved | 2/13/2025 | SELLA BENYAMIN |
| Issued | 2/13/2025 | APPLICANT |
| CofO in Progress | 11/3/2025 | GAREN HAYRAPETYAN |
| CofO Issued | 11/13/2025 | RUBEN SALAS |
| Permit Finaled | 11/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/29/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/30/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/19/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Sewer | 2/19/2025 | Approved | GAREN HAYRAPETYAN |
| Underground Mechanical | 2/19/2025 | Approved | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 2/27/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 3/10/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 3/10/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Special/Order Compliance | 3/11/2025 | Partial Inspection | RAUL OLAGI |
| Underground Mechanical | 3/11/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/27/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 3/27/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/27/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/8/2025 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/14/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/14/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/18/2025 | Not Ready for Inspection | LOUIS ESCOTO |
| Shower Pan | 4/18/2025 | Approved | LOUIS ESCOTO |
| HVAC-Rough | 4/22/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 4/22/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 5/9/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/12/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 5/12/2025 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 5/12/2025 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 5/12/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/13/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/19/2025 | Approved | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 6/2/2025 | Conditional Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/23/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 6/23/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 6/23/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 6/23/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 6/23/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 7/11/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/5/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 8/5/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 8/5/2025 | Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 8/5/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 8/5/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 9/17/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Service/Power Release | 9/17/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 9/22/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Service/Power Release | 9/22/2025 | Approved | WAYNE REGESTER |
| Final | 9/25/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 10/24/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 10/31/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 11/3/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| HVAC-Final | 11/3/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 11/3/2025 | SGSOV Approved | GAREN HAYRAPETYAN |