7804 N FERNCOLA AVE 91352
Certificate Information: 7804 N FERNCOLA AVE 91352
- Application / Permit
- 25010-20000-00058
- Plan Check / Job No.
- B25VN00249
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: New Detached 2-Story ADU per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 4/16/2025
- Issuing Office
- Current Status
- CofO Issued on 1/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | DAVID CASTILLO |
| Corrections Issued | 1/21/2025 | DAVID CASTILLO |
| Quality Review Completed | 1/28/2025 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 3/28/2025 | DAVID CASTILLO |
| Plan Check Approved | 4/15/2025 | DAVID CASTILLO |
| Issued | 4/16/2025 | APPLICANT |
| CofO in Progress | 12/12/2025 | DAVID ANDERSON |
| CofO in Progress | 12/26/2025 | DAVID ANDERSON |
| CofO in Progress | 12/26/2025 | DAVID ANDERSON |
| CofO in Progress | 12/27/2025 | DAVID ANDERSON |
| Permit Finaled | 1/15/2026 | RUBEN SALAS |
| CofO Issued | 1/15/2026 | RUBEN SALAS |
| Permit Finaled | 1/15/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/31/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/3/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: NA76761 | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/8/2025 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 5/20/2025 | Partial Approval | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2025 | Partial Approval | DAVID MATSON |
| Deputy Wood Construction | 7/22/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 7/25/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 7/25/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 7/25/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/5/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/5/2025 | Partial Approval | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 8/5/2025 | Approved | DAVID ANDERSON |
| Shower Pan | 8/5/2025 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 8/5/2025 | Approved | DAVID ANDERSON |
| Insulation | 8/7/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 8/13/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/13/2025 | Approved | DAVID ANDERSON |
| Final | 12/2/2025 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 12/2/2025 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 12/2/2025 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 12/2/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 12/2/2025 | Approved | DAVID ANDERSON |
| Final | 12/11/2025 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 12/11/2025 | Approved | DAVID ANDERSON |
| Final | 12/26/2025 | OK to Issue CofO | DAVID ANDERSON |