7804 N FERNCOLA AVE 91352

Certificate Information: 7804 N FERNCOLA AVE 91352

Application / Permit
25010-20000-00058
Plan Check / Job No.
B25VN00249
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: New Detached 2-Story ADU per LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 4/16/2025
Issuing Office
Current Status
CofO Issued on 1/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2025 APPLICANT
Assigned to Plan Check Engineer 1/16/2025 DAVID CASTILLO
Corrections Issued 1/21/2025 DAVID CASTILLO
Quality Review Completed 1/28/2025 CHIHARU SUZUKI
Applicant returned to address corrections 3/28/2025 DAVID CASTILLO
Plan Check Approved 4/15/2025 DAVID CASTILLO
Issued 4/16/2025 APPLICANT
CofO in Progress 12/12/2025 DAVID ANDERSON
CofO in Progress 12/26/2025 DAVID ANDERSON
CofO in Progress 12/26/2025 DAVID ANDERSON
CofO in Progress 12/27/2025 DAVID ANDERSON
Permit Finaled 1/15/2026 RUBEN SALAS
CofO Issued 1/15/2026 RUBEN SALAS
Permit Finaled 1/15/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/31/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/31/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/3/2025 CARLOS AGUILERA
Sewer availability Cleared 2/3/2025 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: NA76761       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/8/2025 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 5/20/2025 Partial Approval DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 5/27/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 6/9/2025 Partial Approval DAVID MATSON
Deputy Wood Construction 7/22/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 7/25/2025 Corrections Issued JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 7/25/2025 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 7/25/2025 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/5/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 8/5/2025 Partial Approval DAVID ANDERSON
Rough-Elec/Plmb/HVAC 8/5/2025 Approved DAVID ANDERSON
Shower Pan 8/5/2025 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 8/5/2025 Approved DAVID ANDERSON
Insulation 8/7/2025 Approved MATTHEW NELSON
Drywall Nailing 8/13/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 8/13/2025 Approved DAVID ANDERSON
Final 12/2/2025 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 12/2/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 12/2/2025 SGSOV Approved DAVID ANDERSON
Service/Power Release 12/2/2025 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 12/2/2025 Approved DAVID ANDERSON
Final 12/11/2025 OK to Issue CofO DAVID ANDERSON
Service/Power Release 12/11/2025 Approved DAVID ANDERSON
Final 12/26/2025 OK to Issue CofO DAVID ANDERSON