700 W 52ND ST 90037

Certificate Information: 700 W 52ND ST 90037

Application / Permit
25010-20000-00041
Plan Check / Job No.
B24VN26439
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT) **ePlan**
Permit Issued
Issued on 7/9/2025
Issuing Office
Current Status
CofO Issued on 3/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2024 APPLICANT
Assigned to Plan Check Engineer 1/2/2025 NILOOFAR MEHRAIN
Corrections Issued 1/5/2025 NILOOFAR MEHRAIN
Quality Review Completed 1/7/2025 JASON HEALEY
Applicant returned to address corrections 5/29/2025 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/17/2025 NILOOFAR MEHRAIN
Plan Check Approved 6/23/2025 NILOOFAR MEHRAIN
Issued 7/9/2025 APPLICANT
CofO in Progress 3/5/2026 SABAS ALONSO
Permit Finaled 3/5/2026 DEROLD HAUFF
CofO Issued 3/5/2026 DEROLD HAUFF
Permit Finaled 3/5/2026 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 1/22/2025 MANERI ROMAN
Hydrant and Access approval Cleared 1/22/2025 JERRY KAO
Low Impact Development (LID) Cleared 1/22/2025 ERNEST TSE
Community Plan Implem. Overlay Cleared 1/23/2025 MANERI ROMAN
Trees in Parkway Cleared 1/31/2025 MIGUEL ORNELAS
Address approval Cleared 2/1/2025 JESSICA OPINION
Permit Cleared 2/1/2025 JESSICA OPINION
Roof/Waste drainage to street Cleared 2/1/2025 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 2/7/2025 JESSICA OPINION
Sewer availability Cleared 2/7/2025 JESSICA OPINION
Community Plan Implem. Overlay Cleared 4/2/2025 JESSICA OPINION
Flood clearance Cleared 4/10/2025 SAMSON WONG
Community Plan Implem. Overlay Cleared 4/17/2025 NILOOFAR MEHRAIN
Community Plan Implem. Overlay Cleared 5/9/2025 RIDWAN HARDY

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/22/2025 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 7/23/2025 Approved SABAS ALONSO
Footing/Foundation/Slab 7/23/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/14/2025 Partial Approval SABAS ALONSO
Deputy Wood Construction 8/26/2025 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Corrections Issued SABAS ALONSO
Sewer 9/2/2025 Approved SABAS ALONSO
Underground Mechanical 9/2/2025 Corrections Issued SABAS ALONSO
Underground Mechanical 9/4/2025 Partial Approval SALVADOR MARTINEZ
ELECTRICAL-Rough 10/1/2025 Approved SABAS ALONSO
HVAC-Rough 10/1/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/10/2025 Corrections Issued SABAS ALONSO
Green Building Rough 10/10/2025 Corrections Issued SABAS ALONSO
PLUMBING-Rough 10/10/2025 Approved SABAS ALONSO
Verify Sprinkler Sign Off 10/10/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/14/2025 Approved SABAS ALONSO
Green Building Rough 10/14/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 10/14/2025 Partial Approval SABAS ALONSO
Insulation 10/20/2025 Approved ANTHONY RAMOS
Drywall Nailing 10/27/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 10/27/2025 Approved ANTHONY RAMOS
Underground Mechanical 12/16/2025 Approved SABAS ALONSO
Underground Mechanical 12/18/2025 Partial Inspection SCOTT FINNILA
ELECTRICAL-Final 2/17/2026 Approved SABAS ALONSO
Gas Test 2/17/2026 Approved SABAS ALONSO
PLUMBING-Final 2/17/2026 Approved SABAS ALONSO
Final 2/18/2026 Corrections Issued SABAS ALONSO
Gas Test 2/18/2026 Approved SABAS ALONSO
Green Building Final 2/18/2026 Approved SABAS ALONSO
HVAC-Final 2/18/2026 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Not Ready SABAS ALONSO
Service/Power Release 2/18/2026 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 2/18/2026 Approved SABAS ALONSO
Final 2/25/2026 Corrections Issued SABAS ALONSO
HVAC-Final 2/25/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/25/2026 SGSOV Approved SABAS ALONSO
Service/Power Release 2/25/2026 Approved SABAS ALONSO
Final 3/2/2026 OK to Issue CofO SABAS ALONSO