8355 1/2 N JUMILLA AVE 91306
Certificate Information: 8355 1/2 N JUMILLA AVE 91306
- Application / Permit
- 25010-20000-00033
- Plan Check / Job No.
- B25VN00129
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ALL ELECTRIC ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g)
- Permit Issued
- Issued on 1/24/2025
- Issuing Office
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 1/14/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/17/2025 | APPLICANT |
| Plan Check Approved | 1/24/2025 | ANGELICA MARTINEZ |
| Issued | 1/24/2025 | APPLICANT |
| CofO in Progress | 7/15/2025 | CHRIS CHRISTENSEN |
| CofO Issued | 7/31/2025 | DANIEL ORRANTE |
| Permit Finaled | 7/31/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2025 | KEVIN CHUNG |
| Roof/Waste drainage to street | Cleared | 1/21/2025 | KEVIN CHUNG |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2025 | KEVIN CHUNG |
| Sewer availability | Cleared | 1/22/2025 | KEVIN CHUNG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/19/2025 | Conditional Approval | JOHN COLEMAN |
| Footing/Foundation/Slab | 3/6/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Partial Approval | JEFFREY HARTLINE |
| Rough-Elec/Plmb/HVAC | 4/7/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Sewer | 4/7/2025 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 4/7/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 4/15/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 4/15/2025 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 4/15/2025 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/17/2025 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/17/2025 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 4/17/2025 | Approved | CHRIS CHRISTENSEN |
| Insulation | 4/21/2025 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 4/28/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 7/7/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 7/7/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 7/7/2025 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 7/7/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 7/7/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 7/14/2025 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 7/14/2025 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 7/14/2025 | Approved | CHRIS CHRISTENSEN |