14161 W REMINGTON ST 91331

Certificate Information: 14161 W REMINGTON ST 91331

Application / Permit
25010-20000-00018
Plan Check / Job No.
B25VN00072
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan - New detached ADU per 66323(A)(2)
Permit Issued
Issued on 3/7/2025
Issuing Office
Current Status
CofO Issued on 9/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2025 APPLICANT
Assigned to Plan Check Engineer 1/8/2025 JOHN MESIAS
Corrections Issued 1/9/2025 JOHN MESIAS
Plan Check Approved 3/5/2025 ZAW HAN
Issued 3/7/2025 APPLICANT
CofO in Progress 9/5/2025 MICHEL ABAJAN
Permit Finaled 9/10/2025 RUBEN SALAS
CofO Issued 9/10/2025 RUBEN SALAS
Permit Finaled 9/10/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/15/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/15/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/15/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/16/2025 LEE GUILBEAUX
Sewer availability Cleared 1/16/2025 LEE GUILBEAUX
Construction near power lines Cleared 2/26/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng D; Lic. No.: NA58075       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/1/2025 Partial Approval MICHEL ABAJAN
Underground Mechanical 4/1/2025 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 4/4/2025 Approved MICHEL ABAJAN
Footing/Foundation/Slab 4/4/2025 Approved MICHEL ABAJAN
Deputy Wood Construction 4/25/2025 Conditional Approval RAUL OLAGI
ELECTRICAL-Rough 4/25/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Partial Approval MICHEL ABAJAN
Green Building Rough 4/25/2025 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 4/25/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 4/25/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 4/25/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/29/2025 Approved MICHEL ABAJAN
Green Building Rough 4/29/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/29/2025 Approved MICHEL ABAJAN
Insulation 5/1/2025 Approved MICHEL ABAJAN
Drywall Nailing 5/6/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/6/2025 Approved MICHEL ABAJAN
Final 7/21/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 7/21/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/21/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 7/21/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 7/21/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 9/3/2025 Approved MICHEL ABAJAN
Final 9/3/2025 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 9/3/2025 Approved MICHEL ABAJAN
PLUMBING-Final 9/3/2025 Approved MICHEL ABAJAN
Service/Power Release 9/3/2025 Approved MICHEL ABAJAN