4605 N VESPER AVE 91403

Certificate Information: 4605 N VESPER AVE 91403

Application / Permit
25010-20000-00016
Plan Check / Job No.
B25VN00062
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL INT & EXT WALLS, KEEP PORTION OF (E) FOUNDATION AND ERECT AN IRR. SHAPED 39'-8" x 90'-9" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE; OPEN TRELLIS, & ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33(c) and (e)]; NFPA-13D THRU OUT
Permit Issued
Issued on 6/4/2025
Issuing Office
Valley
Current Status
Issued on 6/4/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/2/2025 APPLICANT
Assigned to Plan Check Engineer 1/16/2025 SEAN SHAHMIRI
Corrections Issued 1/29/2025 SEAN SHAHMIRI
Building Plans Picked Up 1/31/2025 APPLICANT
Quality Review Completed 2/3/2025 STEVEN KIM
Applicant returned to address corrections 3/10/2025 SEAN SHAHMIRI
Plan Check Approved 3/17/2025 SEAN SHAHMIRI
Issued 6/4/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/6/2025 BIAINA HARITUNIAN
Miscellaneous Cleared 2/6/2025 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 2/7/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/7/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 2/20/2025 CARLOS AGUILERA
Trees in Parkway Cleared 2/24/2025 BRANDON WONG
Permit Cleared 2/25/2025 LEE GUILBEAUX
ZI Cleared 2/25/2025 BRENNEN OBETO
Hydrant and Access approval Cleared 3/3/2025 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/1/2025 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 7/8/2025 Corrections Issued JENNIFER RABUCHIN
Deputy Drilled-In Anchors 7/24/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 8/1/2025 Corrections Issued MISAEL ESPARZA
Green Building Rough 8/1/2025 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 8/1/2025 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 8/13/2025 Partial Approval MISAEL ESPARZA
Green Building Rough 8/13/2025 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 8/13/2025 Not Ready for Inspection MISAEL ESPARZA
Deputy Wood Construction 9/25/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 10/27/2025 Corrections Issued MISAEL ESPARZA
HVAC-Rough 10/27/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 11/3/2025 Approved MISAEL ESPARZA
HVAC-Rough 11/3/2025 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 11/5/2025 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 11/12/2025 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 11/13/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 11/17/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 11/17/2025 Conditional Approval MISAEL ESPARZA
BUILDING-Rough-Frame 11/21/2025 Corrections Issued MISAEL ESPARZA
Green Building Rough 11/21/2025 Approved MISAEL ESPARZA
MERV13>=Rough 11/21/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 12/2/2025 Conditional Approval MISAEL ESPARZA
Insulation 12/2/2025 Corrections Issued MISAEL ESPARZA
Drywall Nailing 12/16/2025 Partial Approval MISAEL ESPARZA
Insulation 12/16/2025 Approved MISAEL ESPARZA
Drywall Nailing 12/19/2025 Approved DAVID MATSON
Shower Pan 12/26/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 1/15/2026 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 2/26/2026 Approved MISAEL ESPARZA
Sewer 4/14/2026 Approved MISAEL ESPARZA
Gas Test 4/21/2026 Partial Approval MISAEL ESPARZA
Gas Test 5/22/2026 Partial Approval MISAEL ESPARZA