1754 1/2 W 25TH ST 90018

Certificate Information: 1754 1/2 W 25TH ST 90018

Application / Permit
25010-20000-00015
Plan Check / Job No.
B25VN00021
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/17/2025
Issuing Office
Valley
Current Status
CofO Issued on 11/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2025 APPLICANT
Assigned to Plan Check Engineer 1/8/2025 JESSE ARELLANO
Corrections Issued 1/9/2025 JESSE ARELLANO
Building Plans Picked Up 1/14/2025 APPLICANT
Applicant returned to address corrections 3/7/2025 GIOVANNY CHAVEZ
Issued 3/17/2025 APPLICANT
CofO in Progress 11/14/2025 WILLIAM SIERRA
Permit Finaled 11/16/2025 DEROLD HAUFF
CofO Issued 11/16/2025 DEROLD HAUFF
Permit Finaled 11/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/30/2025 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/30/2025 JEANIE LAM
Roof/Waste drainage to street Cleared 1/30/2025 JEANIE LAM
Sewer availability Cleared 1/30/2025 JEANIE LAM
Construction near power lines Cleared 3/3/2025 RIDWAN HARDY

Contact Information

Contractor Gt Remodeling Inc; Lic. No.: 1091310-B 15250 VENTURA BLVD      SHERMAN OAKS, CA 91403
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/8/2025 Corrections Issued WILLIAM SIERRA
METHANE-Barrier 4/8/2025 Approved WILLIAM SIERRA
METHANE-Subgrade 4/8/2025 Approved WILLIAM SIERRA
Footing/Foundation/Slab 4/21/2025 Approved BRENDAN MORELLI
Sewer 5/2/2025 Approved WILLIAM SIERRA
Wood Frame 5/2/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Corrections Issued WILLIAM SIERRA
Insulation 5/12/2025 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Partial Approval WILLIAM SIERRA
ELECTRICAL-Rough 6/11/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Rough 6/11/2025 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 7/15/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 7/15/2025 Approved WILLIAM SIERRA
Green Building Rough 7/15/2025 Approved WILLIAM SIERRA
HVAC-Rough 7/15/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 7/15/2025 Approved WILLIAM SIERRA
METHANE-Rough 7/15/2025 Approved WILLIAM SIERRA
Verify Sprinkler Sign Off 7/15/2025 Approved WILLIAM SIERRA
Insulation 8/29/2025 Corrections Issued REGINA MENDEZ
Drywall Nailing 9/17/2025 Approved DEVON JACKSON
Insulation 9/17/2025 Approved DEVON JACKSON
Final 11/10/2025 Corrections Issued WILLIAM SIERRA
Green Building Final 11/10/2025 Not Ready for Inspection WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 11/10/2025 SGSOV Not Required WILLIAM SIERRA
Service/Power Release 11/10/2025 Approved WILLIAM SIERRA
Smoke Detectors 11/10/2025 Approved WILLIAM SIERRA
Final 11/14/2025 OK to Issue CofO WILLIAM SIERRA
Green Building Final 11/14/2025 Approved WILLIAM SIERRA