13768-13768 1/2 W JUDD ST 91331

Certificate Information: 13768-13768 1/2 W JUDD ST 91331

Application / Permit
25010-20000-00011
Plan Check / Job No.
B24VN27273
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New two story building with Single Family Dwelling per SB 9 on the first floor and Attached ADU per LAMC 12.22 A.33(c) and (e) on the second floor. NFPA 13D fire sprinklers throughout
Permit Issued
Issued on 4/25/2025
Issuing Office
Current Status
CofO Issued on 2/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2025 APPLICANT
Assigned to Plan Check Engineer 1/16/2025 JESSE VIDUYA
Corrections Issued 1/24/2025 JESSE VIDUYA
Quality Review Completed 1/31/2025 CHAD DOI
Applicant returned to address corrections 4/9/2025 JESSE VIDUYA
Plan Check Approved 4/23/2025 JESSE VIDUYA
Issued 4/25/2025 APPLICANT
CofO in Progress 1/23/2026 MICHEL ABAJAN
Permit Finaled 2/18/2026 RUBEN SALAS
CofO Issued 2/18/2026 RUBEN SALAS
Permit Finaled 2/18/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/7/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/7/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/7/2025 LEE GUILBEAUX
Hydrant and Access approval Cleared 2/11/2025 RUEL COLE
Clean Up Green Up Cleared 2/13/2025 JACQUELINE TORRES
Eng Process Fee Ord 176,300 Cleared 2/13/2025 LEE GUILBEAUX
Sewer availability Cleared 2/13/2025 LEE GUILBEAUX
Senate Bill 9 Cleared 2/20/2025 JACQUELINE TORRES
Construction near power lines Cleared 3/6/2025 ENRIQUE ACOSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Sheppard,, Kayse Rose; Lic. No.: NA95444       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/6/2025 Approved MICHEL ABAJAN
Deputy Reinf. Concrete 5/7/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/15/2025 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 5/16/2025 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 5/20/2025 Partial Approval MICHEL ABAJAN
Insulation 5/23/2025 Partial Approval MICHEL ABAJAN
Wood Frame 6/3/2025 Corrections Issued KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 6/26/2025 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 6/30/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 7/7/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 7/7/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 7/7/2025 Approved MICHEL ABAJAN
Shower Pan 7/15/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 7/17/2025 Approved MICHEL ABAJAN
HVAC-Rough 7/17/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/17/2025 Approved MICHEL ABAJAN
Insulation 7/22/2025 Approved MICHEL ABAJAN
Drywall Nailing 7/29/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 7/31/2025 Approved NICHOLAS TROWBRIDGE
Gas Test 8/5/2025 Approved MICHEL ABAJAN
Underground Mechanical 10/6/2025 Partial Approval MICHEL ABAJAN
Sewer 10/9/2025 Approved KEVIN BERBERYAN
Underground Mechanical 10/9/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 10/14/2025 Approved MICHEL ABAJAN
PLUMBING-Final 10/14/2025 Approved MICHEL ABAJAN
Final 1/9/2026 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/9/2026 SGSOV Approved MICHEL ABAJAN
Service/Power Release 1/9/2026 Approved MICHEL ABAJAN
Smoke Detectors 1/9/2026 Approved MICHEL ABAJAN
Final 1/22/2026 OK to Issue CofO MICHEL ABAJAN