14202 W HAYNES ST 91401

Certificate Information: 14202 W HAYNES ST 91401

Application / Permit
25010-20000-00003
Plan Check / Job No.
B24VN27248
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. New detached 1,100 sq.ft ADU Per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 5/7/2025
Issuing Office
Current Status
CofO in Progress on 1/27/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/3/2025 APPLICANT
Assigned to Plan Check Engineer 1/8/2025 ALFREDO JARA
Corrections Issued 1/12/2025 ALFREDO JARA
Applicant returned to address corrections 3/23/2025 ALFREDO JARA
Plan Check Approved 4/18/2025 ALFREDO JARA
Plan Check Approved 5/6/2025 ALFREDO JARA
Issued 5/7/2025 APPLICANT
CofO in Progress 1/27/2026 RYAN SALAZAR

Permit Application Clearance Information

Address approval Cleared 1/13/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 1/13/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 2/18/2025 RIDWAN HARDY
Construction within easement Cleared 2/18/2025 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 4/1/2025 BIAINA HARITUNIAN
Sewer availability Cleared 4/1/2025 BIAINA HARITUNIAN
CPC Cleared 4/7/2025 NATHALY DE LA PAZ
HPOZ Cleared 4/7/2025 NATHALY DE LA PAZ

Contact Information

Contractor Pacific Point Builders Inc; Lic. No.: 768984-B       ,
Engineer Austin,, James Everett; Lic. No.: NA4782       ,
Engineer Austin,, James Everett; Lic. No.: S4782 PO BOX 1767      TRUCKEE, CA 96160

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/23/2025 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 6/13/2025 Approved RYAN SALAZAR
PLUMBING-Rough 6/13/2025 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/20/2025 Corrections Issued KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 8/20/2025 Corrections Issued KEVIN BERBERYAN
Sewer 8/29/2025 Approved RYAN SALAZAR
Underground Mechanical 8/29/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 9/10/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/10/2025 Approved RYAN SALAZAR
Green Building Rough 9/10/2025 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 9/10/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 9/10/2025 Approved RYAN SALAZAR
Insulation 9/30/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/30/2025 Approved RYAN SALAZAR
Shower Pan 9/30/2025 Approved RYAN SALAZAR
Drywall Nailing 10/6/2025 Approved RYAN SALAZAR
Final 12/23/2025 Not Ready for Inspection RYAN SALAZAR
Green Building Final 12/23/2025 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/23/2025 SGSOV Not Ready RYAN SALAZAR
Service/Power Release 12/23/2025 Not Ready for Inspection RYAN SALAZAR
Underground Mechanical 12/23/2025 Approved RYAN SALAZAR
Final 12/30/2025 Not Ready for Inspection RYAN SALAZAR
Green Building Final 12/30/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 12/30/2025 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 12/30/2025 Not Ready for Inspection RYAN SALAZAR
Final 1/22/2026 OK to Issue CofO RYAN SALAZAR
Service/Power Release 1/22/2026 Approved RYAN SALAZAR
Smoke Detectors 1/22/2026 Approved RYAN SALAZAR