14202 W HAYNES ST 91401
Certificate Information: 14202 W HAYNES ST 91401
- Application / Permit
- 25010-20000-00003
- Plan Check / Job No.
- B24VN27248
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. New detached 1,100 sq.ft ADU Per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/7/2025
- Issuing Office
- Current Status
- CofO in Progress on 1/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2025 | ALFREDO JARA |
| Corrections Issued | 1/12/2025 | ALFREDO JARA |
| Applicant returned to address corrections | 3/23/2025 | ALFREDO JARA |
| Plan Check Approved | 4/18/2025 | ALFREDO JARA |
| Plan Check Approved | 5/6/2025 | ALFREDO JARA |
| Issued | 5/7/2025 | APPLICANT |
| CofO in Progress | 1/27/2026 | RYAN SALAZAR |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/13/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 2/18/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/18/2025 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/1/2025 | BIAINA HARITUNIAN |
| CPC | Cleared | 4/7/2025 | NATHALY DE LA PAZ |
| HPOZ | Cleared | 4/7/2025 | NATHALY DE LA PAZ |
Contact Information
| Contractor | Pacific Point Builders Inc; Lic. No.: 768984-B | , |
| Engineer | Austin,, James Everett; Lic. No.: NA4782 | , |
| Engineer | Austin,, James Everett; Lic. No.: S4782 | PO BOX 1767 TRUCKEE, CA 96160 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/23/2025 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 6/13/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 6/13/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Corrections Issued | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 8/20/2025 | Corrections Issued | KEVIN BERBERYAN |
| Sewer | 8/29/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 8/29/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/10/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/10/2025 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 9/10/2025 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 9/10/2025 | Approved | RYAN SALAZAR |
| Insulation | 9/30/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/30/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 9/30/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 10/6/2025 | Approved | RYAN SALAZAR |
| Final | 12/23/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 12/23/2025 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Not Ready | RYAN SALAZAR |
| Service/Power Release | 12/23/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Underground Mechanical | 12/23/2025 | Approved | RYAN SALAZAR |
| Final | 12/30/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 12/30/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Not Required | RYAN SALAZAR |
| Service/Power Release | 12/30/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 12/30/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 1/22/2026 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 1/22/2026 | Approved | RYAN SALAZAR |
| Smoke Detectors | 1/22/2026 | Approved | RYAN SALAZAR |