300 N BELLINO DR 90272

Certificate Information: 300 N BELLINO DR 90272

Application / Permit
25010-10001-02366
Plan Check / Job No.
B25LA40213
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SUPPLEMENTAL PERMIT TO 25010-10000-02366 FOR JADU ADDITION PER GCS 66323(a)(1) AND 66333 TO SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE, 1-STORY, NFPA 13D SPRINKLER THROUGHOUT. EO1*EPLAN*
Permit Issued
Issued on 2/12/2026
Issuing Office
Current Status
Issued on 2/12/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/25/2025 APPLICANT
Assigned to Plan Check Engineer 10/2/2025 VIVIAN LAO
Corrections Issued 10/7/2025 VIVIAN LAO
Quality Review Completed 10/7/2025 JOHN FRANCIA
Applicant returned to address corrections 1/16/2026 VIVIAN LAO
Plan Check Approved 2/12/2026 VIVIAN LAO
Issued 2/12/2026 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/8/2025 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 10/8/2025 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 10/8/2025 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 10/8/2025 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 10/8/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/8/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/8/2025 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 10/23/2025 MARTIN FRAGOSO
Hydrant and Access approval Cleared 10/28/2025 RUEL COLE
Grading Pre-Inspection Cleared 10/28/2025 LANNY MERRICK
Address approval Cleared 2/11/2026 SAFA JAVANMARDI
GPI Written Notices Cleared 2/12/2026 VIVIAN LAO

Contact Information

Contractor Owner-Builder       ,
Engineer Khanlou,, Amir; Lic. No.: C87550 2603 BASIL LN      LOS ANGELES, CA 90077

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2026 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 2/20/2026 Not Ready for Inspection BOBBY KEY
Underground Mechanical 2/20/2026 Partial Approval BOBBY KEY
Footing/Foundation/Slab 2/23/2026 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 4/8/2026 Corrections Issued BOBBY KEY