6560 W ROMAINE ST 90038
Certificate Information: 6560 W ROMAINE ST 90038
- Application / Permit
- 25010-10001-00002
- Plan Check / Job No.
- B25LA03970
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building for Household Goods
- Work Description
- Foundation Only pemit for 25010-10000-00002: 7 Story PUBLIC STORAGE FACILITY WITH SURFACE PARKING PER CPC-2023-5532-ZC-HD-CU-SPR-WDI.
- Permit Issued
- Issued on 8/29/2025
- Issuing Office
- Current Status
- Issued on 8/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Plan Check Approved | 8/29/2025 | HERNAN ARREOLA |
| Issued | 8/29/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/7/2025 | WALLIE JONG |
| Permit | Cleared | 2/7/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 2/7/2025 | WALLIE JONG |
| Sewer availability | Cleared | 2/7/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2025 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 4/1/2025 | KURT CORRAL |
| DAS Clearance | Cleared | 4/15/2025 | HERNAN ARREOLA |
| "D" conditions | Cleared | 5/12/2025 | DAVID URITA |
| "Q" conditions | Cleared | 5/12/2025 | DAVID URITA |
| "T" removal | Cleared | 5/12/2025 | DAVID URITA |
| Miscellaneous | Cleared | 5/12/2025 | DAVID URITA |
| Miscellaneous | Cleared | 5/12/2025 | DAVID URITA |
| Miscellaneous | Cleared | 5/12/2025 | DAVID URITA |
| Miscellaneous | Cleared | 5/12/2025 | DAVID URITA |
| Green Code | Cleared | 5/15/2025 | AARON COSTA |
| Zoning Plan Check | Cleared | 5/20/2025 | HERNAN ARREOLA |
| Low Impact Development (LID) | Cleared | 5/22/2025 | MITESH PATEL |
| Highway dedication | Cleared | 6/3/2025 | WALLIE JONG |
| Trees in Parkway | Cleared | 8/19/2025 | MIGUEL ORNELAS |
| Building over 36-ft | Cleared | 8/29/2025 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 8/29/2025 | CALOSHA APPROVED |
Contact Information
| Architect | Folonis,, Michael William; Lic. No.: NA13780 | , |
| Contractor | Vertical Construction Inc; Lic. No.: 409490-B | 9955 MUIRLANDS IRVINE, CA 92618 |
| Engineer | Bai,, Feifei; Lic. No.: S6397 | 19830 TIDY TIPS LN SPRING, TX 77379 |
| Engineer | Blunck,, Jerome Jon; Lic. No.: GE151 | 3595 OLD CONEJO ROAD THOUSAND OAKS, CA 91320 |
| Engineer | Savage,, Sean Michael; Lic. No.: NA75677 | , |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/27/2025 | Not Ready for Inspection | JEFFREY FULTON |
| METHANE-Barrier | 10/27/2025 | Not Ready for Inspection | JEFFREY FULTON |
| METHANE-Subgrade | 10/27/2025 | Not Ready for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 10/30/2025 | Not Ready for Inspection | JEFFREY FULTON |
| METHANE-Barrier | 10/30/2025 | Not Ready for Inspection | JEFFREY FULTON |
| METHANE-Subgrade | 10/30/2025 | Not Ready for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 11/7/2025 | Partial Approval | DAVID BURKHEAD |
| METHANE-Barrier | 11/7/2025 | Approved | DAVID BURKHEAD |
| METHANE-Subgrade | 11/7/2025 | Approved | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 12/8/2025 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 12/8/2025 | Not Ready for Inspection | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 12/10/2025 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 12/10/2025 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 12/18/2025 | Approved | DAVID BURKHEAD |
| Footing/Foundation/Slab | 12/18/2025 | Partial Approval | DAVID BURKHEAD |
| Pre-Inspection | 12/18/2025 | Approved | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 4/22/2026 | Conditional Approval | DAVID BURKHEAD |
| Pre-Inspection | 4/22/2026 | Approved | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 4/23/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 4/27/2026 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 5/4/2026 | Partial Approval | DAVID BURKHEAD |
| Green Building Rough | 5/4/2026 | Not Ready for Inspection | DAVID BURKHEAD |
| METHANE-Rough | 5/4/2026 | Not Ready for Inspection | DAVID BURKHEAD |
| Reinforced Concrete Frame | 5/4/2026 | Partial Approval | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 5/4/2026 | Not Ready for Inspection | DAVID BURKHEAD |
| Footing/Foundation/Slab | 5/8/2026 | Partial Approval | DAVID BURKHEAD |
| Deputy Fireproofing | 5/15/2026 | Conditional Approval | DAVID BURKHEAD |
| Deputy Fireproofing | 5/18/2026 | Conditional Approval | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 5/28/2026 | Partial Approval | MARTIN TAVITIAN |
| Deputy Reinf. Concrete | 5/29/2026 | Conditional Approval | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 5/29/2026 | Partial Approval | RONALD JIMENEZ |
| Deputy Reinf. Concrete | 6/1/2026 | Approved | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 6/1/2026 | Partial Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 6/2/2026 | Approved | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 6/2/2026 | Partial Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 6/4/2026 | Approved | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 6/4/2026 | Partial Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 6/11/2026 | Conditional Approval | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 6/11/2026 | Partial Approval | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 6/22/2026 | Partial Approval | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 6/24/2026 | Partial Approval | DAVID BURKHEAD |
| Light Gage Steel Frame | 7/10/2026 | Not Ready for Inspection | RONALD JIMENEZ |