761 N HARTZELL ST 90272
Certificate Information: 761 N HARTZELL ST 90272
- Application / Permit
- 25010-10000-06450
- Plan Check / Job No.
- B25LA54163
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY, 68'-11" x 37'-9". NFPA 13D SPRINKLERS THROUGHOUT EO1 ELIGIBLE
- Permit Issued
- Issued on 3/17/2026
- Issuing Office
- Current Status
- Issued on 3/17/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2025 | VU NGUYEN |
| Corrections Issued | 1/6/2026 | VU NGUYEN |
| Quality Review Completed | 1/6/2026 | EUGENE BARBEAU |
| Applicant returned to address corrections | 1/14/2026 | VU NGUYEN |
| Applicant returned to address corrections | 1/16/2026 | VU NGUYEN |
| Plan Check Approved | 3/17/2026 | VU NGUYEN |
| Issued | 3/17/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2026 | DAVID LOPEZ |
| Permit | Cleared | 1/6/2026 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 1/6/2026 | DAVID LOPEZ |
| Sewer availability | Cleared | 1/6/2026 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 1/12/2026 | KURT CORRAL |
Contact Information
| Contractor | A M G Capital; Lic. No.: 1040753-B | 4911 GENESTA AVE ENCINO, CA 91316 |
| Engineer | Golabtounkar,, Tony Hamid; Lic. No.: C49104 | 1434 WESTWOOD BLVD ST 17 LOS ANGELES, CA 90024 |
| Engineer | Golabtounkar,, Tony Hamid; Lic. No.: NA49104 | , |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/24/2026 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 4/24/2026 | Approved | TEMISTOCLES CAAL |
| Deputy Reinf. Concrete | 4/27/2026 | Conditional Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 5/12/2026 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2026 | Partial Approval | TEMISTOCLES CAAL |
| Insulation | 5/15/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 5/20/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2026 | Corrections Issued | JESUS PINEDA |