570 N LAS CASAS AVE 90272
Certificate Information: 570 N LAS CASAS AVE 90272
- Application / Permit
- 25010-10000-05582
- Plan Check / Job No.
- B25LA46854
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- [ePlan] 2025 WILDFIRE NEW ATACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c), (d), AND (g) 1-STORY, 19'0"x21'6". NFPA 13D SPRINKLERS THROUGHOUT EO1
- Permit Issued
- Issued on 4/3/2026
- Issuing Office
- Current Status
- Issued on 4/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2025 | EDWIN ESPIN |
| Corrections Issued | 11/25/2025 | SELLA BENYAMIN |
| Quality Review Completed | 12/2/2025 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 2/4/2026 | EDWIN ESPIN |
| Applicant returned to address corrections | 3/3/2026 | EDWIN ESPIN |
| Applicant returned to address corrections | 3/12/2026 | EDWIN ESPIN |
| Plan Check Approved | 4/1/2026 | EDWIN ESPIN |
| Issued | 4/3/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 12/3/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 12/3/2025 | MICHAEL BROWN |
| Hydrant and Access approval | Cleared | 1/15/2026 | KURT CORRAL |
| SB8 RUD | Cleared | 3/12/2026 | OLIVIA JIN |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Architect | Noteware,, Brian Arthur; Lic. No.: NA21514 | , |
| Contractor | Mcquade Development Llc; Lic. No.: 1057669-B | 3375 LIVONIA AVE CULVER CITY, CA 90034 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/21/2026 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/29/2026 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 6/8/2026 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 6/8/2026 | Approved | MICHAEL ALLEN |