752 N HARTZELL ST 90272
Certificate Information: 752 N HARTZELL ST 90272
- Application / Permit
- 25010-10000-05559
- Plan Check / Job No.
- B25LA49244
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, TWO-STORY, 82'6'' x 38'. NFPA 13D SPRINKLERS THROUGHOUT EO1.
- Permit Issued
- Issued on 3/17/2026
- Issuing Office
- Current Status
- Issued on 3/17/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2025 | SERGIO GUTIERREZ |
| Corrections Issued | 12/22/2025 | SERGIO GUTIERREZ |
| Quality Review Completed | 12/24/2025 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 2/19/2026 | SERGIO GUTIERREZ |
| Plan Check Approved | 3/13/2026 | SERGIO GUTIERREZ |
| Issued | 3/17/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2025 | DAVID LOPEZ |
| Permit | Cleared | 12/22/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 12/22/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 12/22/2025 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 1/5/2026 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 1/7/2026 | ERNEST TSE |
Contact Information
| Contractor | Mid Construction Group; Lic. No.: 1030925-B | , |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/18/2026 | Partial Inspection | DANIEL VERA |
| Underground Mechanical | 3/31/2026 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 4/7/2026 | Corrections Issued | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 4/8/2026 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 4/8/2026 | Partial Approval | TEMISTOCLES CAAL |
| Pre-Inspection | 4/8/2026 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2026 | Partial Approval | TEMISTOCLES CAAL |
| Structural Steel Frame | 5/1/2026 | No Access for Inspection | MICHAEL ALLEN |
| Structural Steel Frame | 5/5/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |