3578 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3578 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 25010-10000-05556
- Plan Check / Job No.
- B25LA45856
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY DETACHED ADU. TO BE EQUIPPED WITH NFPA13D FIRE SPRINKLERS. ADU PER GC 66323(a)(2).
- Permit Issued
- Issued on 1/16/2026
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/16/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2025 | ADRIANA LOPEZ |
| Assigned to Zoning Architect | 11/6/2025 | MANUEL ZAVALETA |
| Corrections Issued | 11/20/2025 | ADRIANA LOPEZ |
| Quality Review Completed | 11/24/2025 | KEN GILL |
| Building Plans Picked Up | 11/25/2025 | APPLICANT |
| Applicant returned to address corrections | 1/14/2026 | ADRIANA LOPEZ |
| Plan Check Approved | 1/16/2026 | ADRIANA LOPEZ |
| Issued | 1/16/2026 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 11/21/2025 | LUIS LUVANO |
| Address approval | Cleared | 12/12/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 12/12/2025 | CINDY QI |
| Sewer availability | Cleared | 12/12/2025 | CINDY QI |
| Zoning Plan Check | Cleared | 1/5/2026 | MANUEL ZAVALETA |
| GPI Written Notices | Cleared | 1/16/2026 | ADRIANA LOPEZ |
| Grading Pre-Inspection | Cleared | 1/16/2026 | ADRIANA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2026 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2026 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 3/25/2026 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 4/20/2026 | Approved | EUGENE CASSIDY |
| Sewer | 4/20/2026 | Approved | EUGENE CASSIDY |