7314 N GAVIOTA AVE 91406
Certificate Information: 7314 N GAVIOTA AVE 91406
- Application / Permit
- 25010-10000-05489
- Plan Check / Job No.
- B25LA48557
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER STATE GC 66323(a)(2)
- Permit Issued
- Issued on 1/5/2026
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2025 | LUKE GONZALES |
| Corrections Issued | 11/22/2025 | LUKE GONZALES |
| Building Plans Picked Up | 11/26/2025 | APPLICANT |
| Applicant returned to address corrections | 12/23/2025 | JOSE VELAZQUEZ |
| Plan Check Approved | 1/2/2026 | ARAMIK SHAHMIRZAIAN |
| Issued | 1/5/2026 | APPLICANT |
| CofO in Progress | 4/29/2026 | KIRK SANDERS |
| Permit Finaled | 6/30/2026 | RUBEN SALAS |
| CofO Issued | 6/30/2026 | RUBEN SALAS |
| Permit Finaled | 6/30/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2025 | JEFF LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2025 | JEFF LOREDO |
| Sewer availability | Cleared | 12/3/2025 | JEFF LOREDO |
| Roof/Waste drainage to street | Cleared | 12/23/2025 | JESUS CISNEROS |
Contact Information
| Contractor | Red Stag Construction Company; Lic. No.: 964664-B | 3211 CAHUENGA BLVD W STE 207 LOS ANGELES, CA 90068 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/9/2026 | Partial Inspection | RYAN SALAZAR |
| Underground Mechanical | 1/20/2026 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/23/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Underground Mechanical | 1/23/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 1/27/2026 | Approved | GAREN HAYRAPETYAN |
| Underground Mechanical | 1/27/2026 | Partial Approval | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 2/13/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2026 | Partial Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 2/13/2026 | Conditional Approval | GAREN HAYRAPETYAN |
| Special/Order Compliance | 2/13/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 2/18/2026 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 2/18/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 2/18/2026 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 2/18/2026 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 2/23/2026 | Approved | JOSE AVILA |
| Insulation | 2/24/2026 | Corrections Issued | MICHAEL CORTEZ |
| Green Building Rough | 2/26/2026 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/2/2026 | Approved | KIRK SANDERS |
| Drywall Nailing | 3/2/2026 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 3/2/2026 | Approved | KIRK SANDERS |
| Final | 4/3/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 4/3/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/3/2026 | SGSOV Not Required | JENNIFER RABUCHIN |
| Service/Power Release | 4/3/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 4/3/2026 | Approved | JENNIFER RABUCHIN |
| Final | 4/24/2026 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 4/24/2026 | Corrections Issued | MATTHEW NELSON |
| Service/Power Release | 4/24/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 4/29/2026 | OK to Issue CofO | KIRK SANDERS |
| Green Building Final | 4/29/2026 | Approved | KIRK SANDERS |
| Service/Power Release | 4/29/2026 | Approved | KIRK SANDERS |