2561-2563 S MIDVALE AVE 90064
Certificate Information: 2561-2563 S MIDVALE AVE 90064
- Application / Permit
- 25010-10000-05476
- Plan Check / Job No.
- B25LA48486
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SFD WITH ATTACHED 2 STORY ADU AND ATTACHED GARAGE.
- Permit Issued
- Issued on 2/6/2026
- Issuing Office
- Metro
- Current Status
- Issued on 2/6/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2025 | VARAND SARKISIAN |
| Assigned to Zoning Architect | 11/20/2025 | SAAD LADHANI |
| Corrections Issued | 11/26/2025 | VARAND SARKISIAN |
| Quality Review Completed | 12/2/2025 | KEN GILL |
| Building Plans Picked Up | 12/5/2025 | APPLICANT |
| Plan Check Approved | 1/27/2026 | VARAND SARKISIAN |
| Issued | 2/6/2026 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/9/2025 | GILBERT URREA |
| Specific Plan | Cleared | 12/9/2025 | RICHARD WOO |
| Address approval | Cleared | 12/12/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 12/12/2025 | CELINA MORENO |
| Sewer availability | Cleared | 12/12/2025 | CELINA MORENO |
| Zoning Plan Check | Cleared | 1/5/2026 | SAAD LADHANI |
| Grading Pre-Inspection | Cleared | 1/27/2026 | VARAND SARKISIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 3/12/2026 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 3/16/2026 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/16/2026 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 3/16/2026 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 3/16/2026 | Partial Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 3/27/2026 | Approved | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Underground Mechanical | 5/26/2026 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2026 | Partial Approval | ASHLEY THOMPSON |
| HVAC-Rough | 6/3/2026 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/3/2026 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/24/2026 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 6/29/2026 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 6/29/2026 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 6/29/2026 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 6/29/2026 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/1/2026 | Partial Approval | DAVID SCANTLIN |
| Shower Pan | 7/6/2026 | Approved | KIRK SANDERS |
| Insulation | 7/17/2026 | Partial Approval | ARAM AVEDISIAN |