5075 N GAVIOTA AVE 91436
Certificate Information: 5075 N GAVIOTA AVE 91436
- Application / Permit
- 25010-10000-05257
- Plan Check / Job No.
- B25LA46816
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *eplan* NEW TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE
- Permit Issued
- Issued on 2/4/2026
- Issuing Office
- Current Status
- Issued on 2/4/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2025 | VARAND SARKISIAN |
| Assigned to Zoning Architect | 11/13/2025 | NEVRIK NAVASARTIAN |
| Corrections Issued | 11/18/2025 | VARAND SARKISIAN |
| Quality Review Completed | 11/21/2025 | GARO TELMI |
| Plan Check Approved | 2/2/2026 | VARAND SARKISIAN |
| Plan Check Approved | 2/4/2026 | INTERNET PERMIT |
| Issued | 2/4/2026 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 11/24/2025 | ERNEST TSE |
| Miscellaneous | Cleared | 11/25/2025 | RUBEN VASQUEZ |
| Hydrant and Access approval | Cleared | 12/10/2025 | GILBERT URREA |
| Address approval | Cleared | 12/12/2025 | ABEL CASILLAS |
| Permit | Cleared | 12/17/2025 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2025 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 12/22/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 12/22/2025 | JEANIE LAM |
| Zoning Plan Check | Cleared | 1/15/2026 | NEVRIK NAVASARTIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/1/2026 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/9/2026 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 4/10/2026 | Conditional Approval | THOMAS FINNILA |
| Deputy Steel/Welding | 4/21/2026 | Partial Approval | SEAN WIRCH |
| Deputy Reinf. Concrete | 4/23/2026 | Partial Approval | SEAN WIRCH |
| Deputy Steel/Welding | 4/24/2026 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2026 | Corrections Issued | THOMAS FINNILA |
| Special/Order Compliance | 5/29/2026 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2026 | Partial Approval | THOMAS FINNILA |