14915 W WHITFIELD AVE 90272

Certificate Information: 14915 W WHITFIELD AVE 90272

Application / Permit
25010-10000-05241
Plan Check / Job No.
B25LA46633
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO1
Permit Issued
Issued on 2/19/2026
Issuing Office
Current Status
Issued on 2/19/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/13/2025 APPLICANT
Assigned to Plan Check Engineer 11/20/2025 JOE VO
Corrections Issued 11/23/2025 JOE VO
Quality Review Completed 11/24/2025 ARMEN JIVALAGIAN
Plan Check Approved 1/23/2026 JOE VO
Issued 2/19/2026 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/25/2025 DAVID LOPEZ
BHO/Hillside ordinance Cleared 11/25/2025 DAVID LOPEZ
BHO/Hillside ordinance Cleared 11/25/2025 DAVID LOPEZ
BHO/Hillside ordinance Cleared 11/25/2025 DAVID LOPEZ
BHO/Hillside ordinance Cleared 11/25/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 11/25/2025 DAVID LOPEZ
Permit Cleared 11/25/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 11/25/2025 DAVID LOPEZ
Sewer availability Cleared 11/25/2025 DAVID LOPEZ
Low Impact Development (LID) Cleared 11/26/2025 MITESH PATEL
Hydrant and Access approval Cleared 12/1/2025 KURT CORRAL
GPI Written Notices Cleared 1/23/2026 JOE VO

Contact Information

Architect Abdelsayed,, Marc A; Lic. No.: C38176 280 VIA LINDA VISTA      REDONDO BEACH, CA 90277
Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Excavation/Setback/Form/Re-Bar 6/10/2026    Time Frame: 11-1

Inspection Request History

Pre-Inspection 3/9/2026 Partial Inspection TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 5/11/2026 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 5/11/2026 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 5/11/2026 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 5/18/2026 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 5/18/2026 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 6/4/2026 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 6/4/2026 Partial Approval JESUS PINEDA
PLUMBING-Rough 6/5/2026 Partial Inspection EVAN COOPER