1051 N EMBURY ST 90272

Certificate Information: 1051 N EMBURY ST 90272

Application / Permit
25010-10000-05198
Plan Check / Job No.
B25LA46159
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING . NFPA 13D SPRINKLERS THROUGHOUT. EO1
Permit Issued
Issued on 2/19/2026
Issuing Office
Current Status
Issued on 2/19/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/19/2025 APPLICANT
Assigned to Plan Check Engineer 11/20/2025 VU NGUYEN
Corrections Issued 12/1/2025 VU NGUYEN
Quality Review Completed 12/2/2025 EUGENE BARBEAU
Applicant returned to address corrections 1/2/2026 VU NGUYEN
Applicant returned to address corrections 1/8/2026 VU NGUYEN
Plan Check Approved 1/12/2026 VU NGUYEN
Issued 2/19/2026 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/11/2025 CINDY QI
Roof/Waste drainage to street Cleared 12/11/2025 CINDY QI
Sewer availability Cleared 12/11/2025 CINDY QI
Hydrant and Access approval Cleared 12/15/2025 RUEL COLE

Contact Information

Contractor Gleicher Associates Inc; Lic. No.: 759307-B       ,
Engineer Lewis,, Richard; Lic. No.: C90522 6044 HALM AVE      LOS ANGELES, CA 90056

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Floor/Roof Diaphrgm/Shear Wall 7/24/2026   

Inspection Request History

Pre-Inspection 4/6/2026 Partial Inspection TEMISTOCLES CAAL
Pre-Inspection 4/13/2026 Partial Inspection TEMISTOCLES CAAL
PLUMBING-Rough 4/22/2026 Not Ready for Inspection DANIEL VERA
Underground Mechanical 4/22/2026 Approved DANIEL VERA
Deputy Reinf. Concrete 4/24/2026 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/27/2026 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 4/27/2026 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 5/8/2026 Partial Approval STEPHANIE SWANSON
Pre-Inspection 5/13/2026 Partial Inspection TEMISTOCLES CAAL
Footing/Foundation/Slab 5/29/2026 Partial Approval MEL KHACHATOURIAN
Pre-Inspection 6/30/2026 Partial Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/7/2026 Partial Approval JESUS PINEDA
Deputy Wood Construction 7/14/2026 Conditional Approval DAVID FEILER
Wood Frame 7/21/2026 Corrections Issued TEMISTOCLES CAAL