1051 N EMBURY ST 90272
Certificate Information: 1051 N EMBURY ST 90272
- Application / Permit
- 25010-10000-05198
- Plan Check / Job No.
- B25LA46159
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING . NFPA 13D SPRINKLERS THROUGHOUT. EO1
- Permit Issued
- Issued on 2/19/2026
- Issuing Office
- Current Status
- Issued on 2/19/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2025 | VU NGUYEN |
| Corrections Issued | 12/1/2025 | VU NGUYEN |
| Quality Review Completed | 12/2/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 1/2/2026 | VU NGUYEN |
| Applicant returned to address corrections | 1/8/2026 | VU NGUYEN |
| Plan Check Approved | 1/12/2026 | VU NGUYEN |
| Issued | 2/19/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 12/11/2025 | CINDY QI |
| Sewer availability | Cleared | 12/11/2025 | CINDY QI |
| Hydrant and Access approval | Cleared | 12/15/2025 | RUEL COLE |
Contact Information
| Contractor | Gleicher Associates Inc; Lic. No.: 759307-B | , |
| Engineer | Lewis,, Richard; Lic. No.: C90522 | 6044 HALM AVE LOS ANGELES, CA 90056 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2026 |
Inspection Request History
| Pre-Inspection | 4/6/2026 | Partial Inspection | TEMISTOCLES CAAL |
| Pre-Inspection | 4/13/2026 | Partial Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/22/2026 | Not Ready for Inspection | DANIEL VERA |
| Underground Mechanical | 4/22/2026 | Approved | DANIEL VERA |
| Deputy Reinf. Concrete | 4/24/2026 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/27/2026 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 4/27/2026 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 5/8/2026 | Partial Approval | STEPHANIE SWANSON |
| Pre-Inspection | 5/13/2026 | Partial Inspection | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 5/29/2026 | Partial Approval | MEL KHACHATOURIAN |
| Pre-Inspection | 6/30/2026 | Partial Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2026 | Partial Approval | JESUS PINEDA |
| Deputy Wood Construction | 7/14/2026 | Conditional Approval | DAVID FEILER |
| Wood Frame | 7/21/2026 | Corrections Issued | TEMISTOCLES CAAL |