611 N TOYOPA DR 90272
Certificate Information: 611 N TOYOPA DR 90272
- Application / Permit
- 25010-10000-05146
- Plan Check / Job No.
- B25LA45823
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **2025 WILDFIRE ELIGIBLE PROJECT** EPLAN. NEW ONE STORY DETACHED ADU PER GC 66323(a)(2)
- Permit Issued
- Issued on 11/24/2025
- Issuing Office
- Current Status
- Issued on 11/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2025 | ADAM HEGAZI |
| Corrections Issued | 11/5/2025 | ADAM HEGAZI |
| Applicant returned to address corrections | 11/14/2025 | ADAM HEGAZI |
| Plan Check Approved | 11/18/2025 | ADAM HEGAZI |
| Issued | 11/24/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/6/2025 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2025 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 11/6/2025 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 11/6/2025 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 11/13/2025 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 11/14/2025 | LANNY MERRICK |
Contact Information
| Contractor | Radd Construction; Lic. No.: 922522-B | , |
| Engineer | Golabtounkar,, Tony Hamid; Lic. No.: NA49104 | , |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/29/2025 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 12/30/2025 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 1/13/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 1/13/2026 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2026 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 1/13/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 1/13/2026 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 1/13/2026 | Corrections Issued | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 2/25/2026 | Conditional Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 2/25/2026 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 2/25/2026 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 2/25/2026 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 2/25/2026 | Partial Approval | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 2/25/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Shower Pan | 2/26/2026 | Approved | MEL KHACHATOURIAN |
| Insulation | 3/2/2026 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 3/5/2026 | Approved | DANIEL VERA |
| Drywall Nailing | 3/12/2026 | Approved | HERBERT GIRON |