16769-16771 W ADDISON ST 91436

Certificate Information: 16769-16771 W ADDISON ST 91436

Application / Permit
25010-10000-04900
Plan Check / Job No.
B25LA43856
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE, ATTACHED ACCESSORY DWELLING UNIT (764.7 SF) PER LAMC 12.22A.33(c) AND (e) AND TRELLIS COVER (133.9 SF). NFPA 13D. SOLAR INSTALLATION REQUIRED TO MEET KW PER TITLE 24 PRIOR TO COFO.
Permit Issued
Issued on 2/25/2026
Issuing Office
Current Status
Issued on 2/25/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/20/2025 APPLICANT
Assigned to Plan Check Engineer 10/23/2025 VIVIAN LAO
Assigned to Zoning Architect 10/23/2025 KRISTEL MARQUEZ
Corrections Issued 10/30/2025 VIVIAN LAO
Quality Review Completed 11/6/2025 GARO TELMI
Applicant returned to address corrections 2/2/2026 VIVIAN LAO
Applicant returned to address corrections 2/17/2026 VIVIAN LAO
Plan Check Approved 2/24/2026 VIVIAN LAO
Issued 2/25/2026 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 11/12/2025 ERNEST TSE
Hydrant and Access approval Cleared 11/15/2025 LAVEON RIDER
Address approval Cleared 11/21/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/21/2025 CARLOS AGUILERA
Permit Cleared 11/21/2025 CARLOS AGUILERA
Sewer availability Cleared 11/21/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/8/2025 CARLOS AGUILERA
Zoning Plan Check Cleared 1/20/2026 KRISTEL MARQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

BUILDING-Rough-Frame 7/24/2026   
Green Building Rough 7/24/2026   
PLUMBING-Rough 7/24/2026   
HVAC-Rough 7/24/2026   
ELECTRICAL-Rough 7/24/2026   

Inspection Request History

PLUMBING-Rough 3/11/2026 Partial Approval ROBERT GOLD
Sewer 3/11/2026 Approved ROBERT GOLD
Excavation/Setback/Form/Re-Bar 3/19/2026 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 3/19/2026 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 3/23/2026 Partial Approval THOMAS FINNILA
Underground Mechanical 3/23/2026 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 3/25/2026 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 3/31/2026 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 4/1/2026 Approved THOMAS FINNILA
Deputy Wood Construction 4/23/2026 Conditional Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 4/23/2026 Partial Approval THOMAS FINNILA
Pre-Inspection 5/7/2026 Partial Inspection THOMAS FINNILA
Deputy Steel/Welding 5/8/2026 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/12/2026 Partial Approval THOMAS FINNILA
Pre-Inspection 5/12/2026 Partial Inspection THOMAS FINNILA
BUILDING-Rough-Frame 5/15/2026 Partial Approval ROBERT GOLD
Pre-Inspection 5/20/2026 Partial Inspection ROBERT GOLD
Pre-Inspection 5/29/2026 Partial Approval THOMAS FINNILA
Pre-Inspection 6/3/2026 Partial Approval THOMAS FINNILA
PLUMBING-Rough 6/10/2026 Corrections Issued ROBERT GOLD
ELECTRICAL-Rough 6/18/2026 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 6/29/2026 Corrections Issued SEAN WIRCH
ELECTRICAL-Rough 6/29/2026 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 6/29/2026 Partial Approval SEAN WIRCH
PLUMBING-Rough 6/29/2026 Corrections Issued SEAN WIRCH
BUILDING-Rough-Frame 7/7/2026 Corrections Issued THOMAS FINNILA
Green Building Rough 7/7/2026 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 7/7/2026 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 7/7/2026 Corrections Issued THOMAS FINNILA
Verify Sprinkler Sign Off 7/7/2026 Approved THOMAS FINNILA